1240 S FIGUEROA ST Level 1 90015

Certificate Information: 1240 S FIGUEROA ST Level 1 90015

Application / Permit
23016-10000-03817
Plan Check / Job No.
B23LA02321
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Tenant Improvement for existing core and shell restaurant space on the ground floor. New sports bar restaurant with interior and outdoor seating. Outdoor trellis for seating. A2 - Restaurant/Bar. Type 1A. Fully sprinkled.
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
Permit Finaled on 3/7/2024

Permit Application Status History

Submitted 2/10/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 HERNAN ARREOLA
Corrections Issued 3/5/2023 HERNAN ARREOLA
Quality Review Completed 3/15/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 5/10/2023 HERNAN ARREOLA
Applicant returned to address corrections 6/9/2023 HERNAN ARREOLA
Applicant returned to address corrections 9/6/2023 HERNAN ARREOLA
Plan Check Approved 9/27/2023 HERNAN ARREOLA
Issued 9/28/2023 APPLICANT
Permit Finaled 3/6/2024 JEROME BLACKWOOD

Permit Application Clearance Information

Redevelopment Project Area Cleared 7/3/2023 YASMINE BASHIRI
Fire Marshal Fire Life Safety Cleared 8/7/2023 ANDREW KO
Food establishment approval Cleared 9/11/2023 LACDHS APPROVED
DAS Clearance Cleared 9/18/2023 Sarkis Harabedian
Food Service Establishment Cleared 9/20/2023 RAMESHBHAIR PATEL
Green Code Cleared 9/20/2023 Sarkis Harabedian

Contact Information

Contractor Curato Design/Build; Lic. No.: 1045316-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 10/6/2023 Corrections Issued KATY RAMIREZ
Drywall Nailing 10/10/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 10/16/2023 Corrections Issued KATY RAMIREZ
Insulation 10/20/2023 Approved KATY RAMIREZ
Drywall Nailing 10/30/2023 Partial Approval KATY RAMIREZ
Pre-Inspection 10/31/2023 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 11/28/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 12/5/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 12/15/2023 Partial Approval KATY RAMIREZ
T-Bar Ceiling 12/18/2023 Partial Approval MARTIN TAVITIAN
Special/Order Compliance 12/22/2023 Corrections Issued NICK DANERI
Final 1/30/2024 Partial Inspection KATY RAMIREZ
Green Building Final 1/30/2024 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved RICARDO ROBLES
Smoke Detectors 1/30/2024 Approved KATY RAMIREZ
Final 3/6/2024 Permit Finaled JEROME BLACKWOOD