2418 N CANYON DR 90068

Certificate Information: 2418 N CANYON DR 90068

Application / Permit
23016-10000-03594
Plan Check / Job No.
B23LA02173
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A NEW 18'-0" x 18'-0" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/20/2023
Issuing Office
Current Status
Issued on 3/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/8/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 SARKIS HARABEDIAN
Corrections Issued 2/19/2023 SARKIS HARABEDIAN
Applicant returned to address corrections 3/14/2023 SARKIS HARABEDIAN
Plan Check Approved 3/18/2023 SARKIS HARABEDIAN
Issued 3/20/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/3/2023 STEVE MELGAR
Sewer availability Cleared 3/3/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/6/2023 STEVE MELGAR
Hydrant and Access approval Cleared 3/12/2023 KURT CORRAL
"D" conditions Cleared 3/14/2023 LIKYELESH ABERA
ZI Cleared 3/14/2023 LIKYELESH ABERA
Grading Pre-Inspection Cleared 3/18/2023 SARKIS HARABEDIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/16/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/5/2023 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/5/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/22/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/26/2023 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 6/30/2023 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/3/2023 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 7/10/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/13/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/19/2023 Approved JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 8/1/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/2/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 8/2/2023 Approved JOAQUIN GREENOUGH
Insulation 8/4/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 8/7/2023 Approved JOAQUIN GREENOUGH
Shower Pan 8/15/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/29/2023 Approved JOAQUIN GREENOUGH
Final 9/27/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 9/27/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 9/27/2023 Approved JOAQUIN GREENOUGH
Final 10/3/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved JOAQUIN GREENOUGH
Final 10/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 11/1/2023 Corrections Issued JOAQUIN GREENOUGH
Final 11/7/2023 Partial Inspection JOAQUIN GREENOUGH
Final 11/11/2023 Corrections Issued JOAQUIN GREENOUGH