1044 1/2 W 84TH PL 90044
Certificate Information: 1044 1/2 W 84TH PL 90044
- Application / Permit
- 23016-10000-03510
- Plan Check / Job No.
- B23LA02107
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert existing one story detached garage to ADU with covered proch per wfpp and p/bc 2020-006 (Conversion of Accessory Building per State Law, GCS 65852.2(e)(1)(A))
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2023 | DANIEL SANJUAN |
| Corrections Issued | 3/14/2023 | DANIEL SANJUAN |
| Applicant returned to address corrections | 8/31/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 9/5/2023 | SHANGQIN XIE |
| Plan Check Approved | 9/13/2023 | AUNG SOE |
| Issued | 9/28/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | MICHAEL LEWIS |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/20/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | CELINA MORENO |
| Construction near power lines | Cleared | 6/7/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/7/2023 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 8/21/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | A V O Builders Inc; Lic. No.: 1044152-B | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/30/2023 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/30/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 12/13/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 12/13/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/13/2023 | Approved | MICHAEL LEWIS |
| Insulation | 12/21/2023 | Partial Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/8/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 1/8/2024 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/8/2024 | Approved | MICHAEL LEWIS |
| Wood Frame | 1/8/2024 | Approved | MICHAEL LEWIS |
| Insulation | 1/10/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/17/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/17/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/17/2024 | Approved | MICHAEL LEWIS |
| Sewer | 2/9/2024 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 2/9/2024 | Not Ready for Inspection | JOSE MACIAS |
| Sewer | 2/14/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 2/14/2024 | Approved | MICHAEL LEWIS |
| Final | 3/11/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/11/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/11/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/10/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 4/10/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 4/10/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 4/10/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Final | 5/9/2024 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | MICHAEL LEWIS |