1344 N CORONADO ST 90026
Certificate Information: 1344 N CORONADO ST 90026
- Application / Permit
- 23016-10000-03508
- Plan Check / Job No.
- B23LA02103
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A) . CONSTRUCTION WORK IS PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2023 | JOSEPH RAFOLS |
| Corrections Issued | 2/8/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 5/5/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 5/5/2023 | GEORGE ALVAREZ |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 7/11/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
| CofO Issued | 7/13/2025 | DEROLD HAUFF |
| Permit Finaled | 7/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/1/2023 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 5/2/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 8/1/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/8/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 8/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 9/6/2023 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/5/2023 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 10/5/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 10/5/2023 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 10/17/2023 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/17/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 10/17/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/11/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/11/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 12/11/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/11/2023 | Approved | THOMAS LOGRASSO |
| Shower Pan | 12/11/2023 | Approved | THOMAS LOGRASSO |
| Final | 4/25/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 4/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 4/25/2024 | Approved | ROY SPAULDING |
| Final | 6/30/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 6/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 7/11/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 7/11/2025 | Approved | HAMIK HARTOUNIAN |