614 N GOWER ST 90004
Certificate Information: 614 N GOWER ST 90004
- Application / Permit
- 23016-10000-03437
- Plan Check / Job No.
- B23LA02070
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" x 18'-0" GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 08/10/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 11/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 2/19/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 3/23/2023 | FARSHAD ALIMOHAMADI |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 8/22/2024 | EMIL OPFFER |
| Permit Finaled | 11/26/2024 | DANIEL SANCHEZ |
| CofO Issued | 11/26/2024 | DANIEL SANCHEZ |
| Permit Finaled | 11/26/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2023 | CELINA MORENO |
| Sewer availability | Cleared | 3/2/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2023 | CELINA MORENO |
Contact Information
| Contractor | Dhs Ventures Inc; Lic. No.: 1047699-B | , |
| Contractor | La Ccs; Lic. No.: 1047699-B | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2023 | Corrections Issued | PTOLEMY HILL |
| Pre-Inspection | 2/29/2024 | Conditional Approval | EMIL OPFFER |
| Footing/Foundation/Slab | 4/2/2024 | Approved | EMIL OPFFER |
| BUILDING-Rough-Frame | 4/23/2024 | Not Ready for Inspection | EMIL OPFFER |
| Green Building Rough | 4/23/2024 | Not Ready for Inspection | EMIL OPFFER |
| METHANE-Rough | 4/23/2024 | Not Ready for Inspection | EMIL OPFFER |
| PLUMBING-Rough | 5/2/2024 | Corrections Issued | EMIL OPFFER |
| PLUMBING-Rough | 5/7/2024 | Corrections Issued | EMIL OPFFER |
| Wood Frame | 5/7/2024 | Not Ready for Inspection | EMIL OPFFER |
| PLUMBING-Rough | 5/9/2024 | Approved | EMIL OPFFER |
| BUILDING-Rough-Frame | 5/14/2024 | Conditional Approval | EMIL OPFFER |
| Green Building Rough | 5/14/2024 | Conditional Approval | EMIL OPFFER |
| METHANE-Rough | 5/14/2024 | Approved | EMIL OPFFER |
| Insulation | 5/23/2024 | Not Ready for Inspection | COREY HUPP |
| Insulation | 5/29/2024 | Corrections Issued | COREY HUPP |
| Insulation | 6/6/2024 | Not Ready for Inspection | EMIL OPFFER |
| Wood Frame | 6/6/2024 | Partial Inspection | EMIL OPFFER |
| BUILDING-Rough-Frame | 6/7/2024 | Conditional Approval | EMIL OPFFER |
| ELECTRICAL-Rough | 6/7/2024 | Conditional Approval | EMIL OPFFER |
| Grounding or Bonding | 6/7/2024 | Partial Approval | EMIL OPFFER |
| Insulation | 6/7/2024 | Approved | EMIL OPFFER |
| PLUMBING-Rough | 6/7/2024 | Conditional Approval | EMIL OPFFER |
| Green Building Rough | 6/11/2024 | Approved | EMIL OPFFER |
| Drywall Nailing | 6/17/2024 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Approved | COREY HUPP |
| Deputy Wood Construction | 6/18/2024 | Conditional Approval | COREY HUPP |
| Drywall Nailing | 6/25/2024 | Partial Approval | EMIL OPFFER |
| Interior/Exterior Lathing | 6/25/2024 | Conditional Approval | EMIL OPFFER |
| Shower Pan | 6/25/2024 | Not Ready for Inspection | EMIL OPFFER |
| Interior/Exterior Lathing | 6/28/2024 | No Access for Inspection | COREY HUPP |
| Shower Pan | 6/28/2024 | No Access for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 7/1/2024 | Approved | EMIL OPFFER |
| Shower Pan | 7/1/2024 | Approved | EMIL OPFFER |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | EMIL OPFFER |
| Final | 8/21/2024 | OK to Issue CofO | EMIL OPFFER |
| Green Building Final | 8/21/2024 | Approved | EMIL OPFFER |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | EMIL OPFFER |
| Smoke Detectors | 8/21/2024 | Approved | EMIL OPFFER |