10345-10347 W OLETHA LANE 90077
Certificate Information: 10345-10347 W OLETHA LANE 90077
- Application / Permit
- 23016-10000-03424
- Plan Check / Job No.
- B23LA02060
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* SUPPLEMENTAL PERMIT TO 19016-30000-08793 TO CONVERT PORTION OF (E) GARAGE TO ADU AND REDESIGN OF FLOOR PLAN.
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | VIVIAN LAO |
| Corrections Issued | 3/8/2023 | VIVIAN LAO |
| Quality Review Completed | 3/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/2/2023 | VIVIAN LAO |
| Plan Check Approved | 5/11/2023 | VIVIAN LAO |
| Issued | 5/17/2023 | APPLICANT |
| Permit Finaled | 8/1/2024 | SEAN HAUPT |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2023 | DARIN LAM |
| Sewer availability | Cleared | 4/11/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 5/3/2023 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2023 | Partial Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 7/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 7/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/21/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 7/21/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 7/21/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/29/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 9/29/2023 | Approved | BRENDAN LOONEY |
| Insulation | 11/6/2023 | Approved | BRENDAN LOONEY |