835 N LA BREA AVE 90038

Certificate Information: 835 N LA BREA AVE 90038

Application / Permit
23016-10000-03098
Plan Check / Job No.
B23LA01902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
ePLAN- fire damage repair of (E) retail space like-kind repair of building following a fire including replacement of perimeter wall, exterior stucco cladding and interior gypsum board, three glass panes in undamaged window frames.
Permit Issued
Issued on 5/31/2023
Issuing Office
Current Status
Permit Finaled on 1/23/2024

Permit Application Status History

Submitted 2/6/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 MICHAEL LOPEZ
Corrections Issued 2/16/2023 MICHAEL LOPEZ
Applicant returned to address corrections 3/20/2023 MICHAEL LOPEZ
Plan Check Approved 5/25/2023 FARSHAD ALIMOHAMADI
Issued 5/31/2023 APPLICANT
Permit Finaled 1/22/2024 ALFREDO LOPEZ

Permit Application Clearance Information

Address approval Cleared 5/23/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/23/2023 TREVOR QUAN

Contact Information

Contractor A N M Construction Inc; Lic. No.: 835772-B       ,
Contractor Anm Construction And Environmental Services; Lic. No.: 835772-B       ,
Engineer Sandstrom,, Ryan; Lic. No.: NA6364       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 11/30/2023 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 12/19/2023 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 12/19/2023 Partial Approval MARTIN TAVITIAN
Wood Frame 12/19/2023 Partial Approval MARTIN TAVITIAN
Drywall Nailing 12/21/2023 Partial Approval RICARDO ROBLES
Insulation 12/21/2023 Approved RICARDO ROBLES
Drywall Nailing 12/26/2023 Partial Approval JEROME BLACKWOOD
Final 1/16/2024 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 1/16/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 1/22/2024 Permit Finaled ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 1/22/2024 Approved ALFREDO LOPEZ