13016 N EL DORADO AVE 91342

Certificate Information: 13016 N EL DORADO AVE 91342

Application / Permit
23016-10000-03045
Plan Check / Job No.
B23LA01856
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACEHD GARAGE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 5/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 LAWRENCE QUIRANTE
Corrections Issued 2/9/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 2/16/2023 APPLICANT
Plan Check Approved 4/20/2023 WEIJIAN HUANG
Plan Check Approved 4/20/2023 WEIJIAN HUANG
Issued 5/1/2023 APPLICANT
CofO in Progress 4/28/2025 KEVIN BERBERYAN
No Progress 7/10/2025 RAUL OLAGI
CofO in Progress 7/10/2025 RAUL OLAGI
CofO in Progress 9/10/2025 RAUL OLAGI
CofO in Progress 9/10/2025 RAUL OLAGI
Permit Finaled 9/12/2025 RUBEN SALAS
CofO Issued 9/12/2025 RUBEN SALAS
Permit Finaled 9/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/29/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/29/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 3/29/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 4/20/2023 LAWRENCE QUIRANTE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2023 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 8/8/2023 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 8/8/2023 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 8/11/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 8/11/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 8/11/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/31/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/31/2023 Approved MISAEL ESPARZA
Green Building Rough 8/31/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/31/2023 Approved MISAEL ESPARZA
Light Gage Steel Frame 8/31/2023 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 8/31/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/5/2023 Approved KEVIN BERBERYAN
Green Building Final 10/5/2023 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 10/5/2023 Corrections Issued KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 10/5/2023 Approved KEVIN BERBERYAN
Insulation 10/12/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/12/2023 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 10/12/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready KEVIN BERBERYAN
Drywall Nailing 10/19/2023 Approved KEVIN BERBERYAN
Underground Mechanical 11/14/2023 Approved KEVIN BERBERYAN
Underground Mechanical 11/17/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/5/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 2/5/2025 Approved KEVIN BERBERYAN
Final 2/5/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/5/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 2/5/2025 Approved KEVIN BERBERYAN
HVAC-Final 2/5/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 2/5/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 2/5/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 4/16/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/16/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 4/16/2025 Approved KEVIN BERBERYAN
Final 4/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 4/24/2025 Approved KEVIN BERBERYAN
Special/Order Compliance 7/11/2025 Corrections Issued KEVIN BERBERYAN
Final 9/10/2025 OK to Issue CofO RAUL OLAGI