1356 W 36TH PL 90007
Certificate Information: 1356 W 36TH PL 90007
- Application / Permit
- 23016-10000-02883
- Plan Check / Job No.
- B23LA01765
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***ePlan*** Convert existing 2-car detached garage to an accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A); all work done per WFPP.
- Permit Issued
- Issued on 7/21/2023
- Issuing Office
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/11/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 7/14/2023 | ALFREDO JARA |
| Plan Check Approved | 7/19/2023 | CAROLEAN BASMA |
| No Progress | 7/19/2023 | CAROLEAN BASMA |
| Plan Check Approved | 7/19/2023 | CAROLEAN BASMA |
| Issued | 7/21/2023 | APPLICANT |
| CofO in Progress | 8/16/2024 | CRAIG DAVIS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| SB8 RUD | Cleared | 4/4/2023 | JESSICA WANG |
| Roof/Waste drainage to street | Cleared | 4/12/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 4/12/2023 | STEVE MELGAR |
| Address approval | Cleared | 4/27/2023 | STEVE MELGAR |
| Construction near power lines | Cleared | 6/27/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/27/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 10/30/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 11/9/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 11/14/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 11/15/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/15/2023 | Approved | SABAS ALONSO |
| Insulation | 11/15/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 11/17/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/17/2023 | Approved | SABAS ALONSO |
| Insulation | 11/22/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/1/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/1/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| Final | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/6/2024 | Corrections Issued | SABAS ALONSO |
| Gas Test | 3/11/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 3/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 3/11/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 3/18/2024 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 3/21/2024 | Approved | SABAS ALONSO |
| Final | 3/21/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/21/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 3/21/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/21/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/29/2024 | Approved | SABAS ALONSO |
| Final | 3/29/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/29/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 3/29/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 3/29/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | SABAS ALONSO |
| Final | 8/8/2024 | Corrections Issued | SABAS ALONSO |
| Final | 8/12/2024 | No Access for Inspection | CRAIG DAVIS |
| Final | 8/15/2024 | OK to Issue CofO | CRAIG DAVIS |