741 N SPAULDING AVE 90046

Certificate Information: 741 N SPAULDING AVE 90046

Application / Permit
23016-10000-02680
Plan Check / Job No.
B23LA01640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
Remove 88 sq.ft portion of the (E) detached garage and convert 200 sq.ft into recreation room with half bath no shower or bathtub and 195.12 sq.ft into storage.
Permit Issued
Issued on 8/18/2023
Issuing Office
Metro
Current Status
Issued on 8/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/31/2023 APPLICANT
Assigned to Plan Check Engineer 2/4/2023 VICTOR CHEN
Corrections Issued 2/6/2023 VICTOR CHEN
Building Plans Picked Up 2/7/2023 APPLICANT
Applicant returned to address corrections 5/18/2023 SARKIS HARABEDIAN
Plan Check Approved 5/22/2023 MICHAEL LANZONE
No Progress 5/22/2023 MICHAEL LANZONE
Plan Check Approved 5/22/2023 MICHAEL LANZONE
Issued 8/18/2023 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 5/7/2023 RIDWAN HARDY

Contact Information

Architect Ro,, Jungdack; Lic. No.: C31119 4931 MURIETTA AVENUE      SHERMAN OAKS, CA 91423
Contractor R K S Zone Inc; Lic. No.: 961017-B 2333 BEVERLY BLVD #200      LOS ANGELES, CA 90057
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2023 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 10/27/2023 Corrections Issued BRENDAN MORELLI
Pre-Inspection 10/27/2023 Not Ready for Inspection BRENDAN MORELLI
Deputy Drilled-In Anchors 11/7/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 11/13/2023 Corrections Issued LILIANA PORTILLO
METHANE-Rough 11/13/2023 Approved LILIANA PORTILLO
Deputy Wood Construction 11/14/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 11/17/2023 Approved LILIANA PORTILLO
Wood Frame 11/17/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/29/2023 Partial Approval LILIANA PORTILLO
Special/Order Compliance 12/12/2023 Approved LILIANA PORTILLO
Wood Frame 12/12/2023 Conditional Approval LILIANA PORTILLO
Insulation 12/21/2023 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 12/21/2023 Approved LILIANA PORTILLO
Drywall Nailing 1/18/2024 Approved LILIANA PORTILLO
Green Building Rough 1/18/2024 Approved LILIANA PORTILLO
Insulation 1/18/2024 Approved LILIANA PORTILLO
Wood Frame 1/18/2024 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 7/16/2024 No Access for Inspection AMIR NAZARIAN
Final 8/1/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 8/1/2024 Not Ready for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 8/1/2024 Not Ready for Inspection AMIR NAZARIAN
Final 10/31/2025 Corrections Issued RAUL BARAJAS
Green Building Final 10/31/2025 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 10/31/2025 Partial Inspection RAUL BARAJAS