8026 S HOLY CROSS PL 90045
Certificate Information: 8026 S HOLY CROSS PL 90045
- Application / Permit
- 23016-10000-02593
- Plan Check / Job No.
- B23LA00912
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA. GOV STATE CODE 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2023 | ALFRED RAMIREZ |
| Corrections Issued | 1/31/2023 | ROSENDO MEDINA |
| Applicant returned to address corrections | 2/16/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/28/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 3/4/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 4/26/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
| CofO Issued | 4/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/2/2023 | JENSON LEE |
| ZA Case | Cleared | 2/2/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | JENSON LEE |
| Specific Plan | Cleared | 2/13/2023 | PEDRO AYALA |
Contact Information
| Contractor | Forsyth Construction Inc; Lic. No.: 560243-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/28/2023 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 9/28/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/20/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/20/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 11/20/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 11/20/2023 | Approved | BOBBY KEY |
| Green Building Rough | 12/19/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 1/3/2024 | Approved | BOBBY KEY |
| Insulation | 1/3/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 1/12/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/5/2024 | Corrections Issued | BOBBY KEY |
| Final | 4/5/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/5/2024 | Approved | BOBBY KEY |
| HVAC-Final | 4/5/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 4/5/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 4/5/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 4/12/2024 | Approved | BOBBY KEY |
| Final | 4/12/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 4/12/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 4/12/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 4/12/2024 | Approved | BOBBY KEY |
| Final | 4/18/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/18/2024 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 4/18/2024 | Not Ready for Inspection | HERBERT GIRON |
| Final | 4/25/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 4/25/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 4/25/2024 | Approved | JESUS RODRIGUEZ |