6443 W COMMODORE SLOAT DR 90048
Certificate Information: 6443 W COMMODORE SLOAT DR 90048
- Application / Permit
- 23016-10000-02443
- Plan Check / Job No.
- B23LA01480
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Current Status
- CofO Issued on 1/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2023 | DANIEL SMILEY |
| Corrections Issued | 2/7/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 3/5/2023 | KHUONG TRUONG |
| Plan Check Approved | 3/21/2023 | KHUONG TRUONG |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 11/21/2023 | RICHARD DOCKUS |
| No Progress | 12/2/2023 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/4/2023 | RICHARD DOCKUS |
| CofO in Progress | 1/27/2024 | JOAQUIN GREENOUGH |
| Permit Finaled | 1/27/2024 | DEROLD HAUFF |
| CofO Issued | 1/27/2024 | DEROLD HAUFF |
| Permit Finaled | 1/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | JEANIE LAM |
| Sewer availability | Cleared | 2/16/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | JEANIE LAM |
| CPC | Cleared | 2/24/2023 | SPENCER WEJROWSKI |
| City Hist. Cultural Monument | Cleared | 3/17/2023 | JONATHAN KAPLAN |
| HPOZ | Cleared | 3/17/2023 | JONATHAN KAPLAN |
| Historic monument | Cleared | 3/17/2023 | JONATHAN KAPLAN |
Contact Information
| Contractor | Raeen B Construction Inc; Lic. No.: 465214-B | , |
| Engineer | Raeen,, Bahram; Lic. No.: C37060 | 11040 SANTA MONICA BLVD 326 LOS ANGELES, CA 90025 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/16/2023 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/25/2023 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 8/29/2023 | Approved | ROY SPAULDING |
| Gas Test | 8/29/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 8/29/2023 | Not Ready for Inspection | ROY SPAULDING |
| Sewer | 8/29/2023 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 9/7/2023 | Approved | ROY SPAULDING |
| HVAC-Rough | 9/7/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/7/2023 | Approved | ROY SPAULDING |
| Sewer | 9/7/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/8/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 9/8/2023 | Approved | ROY SPAULDING |
| Gas Test | 9/8/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 9/8/2023 | Approved | ROY SPAULDING |
| HVAC-Rough | 9/8/2023 | Approved | ROY SPAULDING |
| Insulation | 9/8/2023 | Not Ready for Inspection | ROY SPAULDING |
| METHANE-Rough | 9/8/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/8/2023 | Approved | ROY SPAULDING |
| Sewer | 9/8/2023 | Approved | ROY SPAULDING |
| Wood Frame | 9/8/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 9/12/2023 | Partial Approval | RICHARD DOCKUS |
| Insulation | 9/15/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/15/2023 | Approved | RONNIE MINDANAO |
| Wood Frame | 9/15/2023 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 9/18/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/18/2023 | Approved | RONNIE MINDANAO |
| Final | 11/8/2023 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 11/8/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/8/2023 | Approved | RICHARD DOCKUS |
| Final | 11/15/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 12/4/2023 | Corrections Issued | RICHARD DOCKUS |
| Final | 1/27/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |