3633 S GREENWOOD AVE 90066

Certificate Information: 3633 S GREENWOOD AVE 90066

Application / Permit
23016-10000-02384
Plan Check / Job No.
B23LA01423
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT PORTION ( approx 11' x 15' 4") OF (E) GARAGE TO JADU PER STATE LAW
Permit Issued
Issued on 3/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/1/2023 WEIJIAN HUANG
Corrections Issued 2/1/2023 WEIJIAN HUANG
Building Plans Picked Up 2/10/2023 APPLICANT
Plan Check Approved 3/21/2023 LUKE GONZALES
Issued 3/21/2023 APPLICANT
CofO in Progress 12/5/2023 JESUS RODRIGUEZ
Permit Finaled 12/7/2023 DANIEL ORRANTE
CofO Issued 12/7/2023 DANIEL ORRANTE
Permit Finaled 12/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/22/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/24/2023 DINAH GARIN
Sewer availability Cleared 2/24/2023 DINAH GARIN
Specific Plan Cleared 2/28/2023 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/8/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 5/8/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/8/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/12/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/19/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/19/2023 Approved JESUS RODRIGUEZ
Insulation 6/2/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/21/2023 Approved EVAN COOPER
ELECTRICAL-Final 10/16/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/16/2023 Approved JESUS RODRIGUEZ
Final 10/23/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 10/23/2023 Corrections Issued JESUS RODRIGUEZ
Final 11/2/2023 Not Ready for Inspection HERBERT GIRON
Green Building Final 11/2/2023 Approved HERBERT GIRON
HVAC-Final 11/2/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/2/2023 Approved HERBERT GIRON
Final 11/6/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 12/1/2023 Partial Approval JESUS RODRIGUEZ
Final 12/4/2023 OK to Issue CofO JESUS RODRIGUEZ