2707-2707 1/4 E FAIRMOUNT ST 90033

Certificate Information: 2707-2707 1/4 E FAIRMOUNT ST 90033

Application / Permit
23016-10000-02342
Plan Check / Job No.
B23LA01396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EXISTING ONE SFD(1248SF) TO BE SPLIT AND CONVERTED TO A DUPLEX WITH UNIT 1(627.25SF) AND UNIT 3(620.75SF).See comments.
Permit Issued
Issued on 5/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/1/2023 GEORGE ALVAREZ
Corrections Issued 2/1/2023 LUKE GONZALES
Building Plans Picked Up 2/2/2023 APPLICANT
Applicant returned to address corrections 3/10/2023 VICTOR CHEN
Applicant returned to address corrections 4/7/2023 KHUONG TRUONG
Applicant returned to address corrections 4/25/2023 ZAW HAN
Plan Check Approved 5/9/2023 SAMUEL GONZALEZ
Issued 5/23/2023 APPLICANT
CofO in Progress 1/24/2024 OSVALDO PARAMO
CofO in Progress 1/24/2024 OSVALDO PARAMO
CofO Issued 3/19/2024 DEROLD HAUFF
Permit Finaled 3/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/4/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/4/2023 TREVOR QUAN
Sewer availability Cleared 4/4/2023 TREVOR QUAN
Tenant Habitability Plan Cleared 4/4/2023 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 4/18/2023 CINDY QI
Grading Pre-Inspection Cleared 4/19/2023 KIRK LINKLATER

Contact Information

Contractor Tass - Onn Construction; Lic. No.: 849637-B 13601 WINGO ST      ARLETA, CA 91331

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/20/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/20/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 6/20/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 6/30/2023 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 7/19/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/2/2023 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 8/2/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 8/2/2023 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 8/15/2023 Approved OSVALDO PARAMO
HVAC-Rough 8/15/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/21/2023 Approved OSVALDO PARAMO
Green Building Rough 8/21/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 8/21/2023 Approved OSVALDO PARAMO
Insulation 8/25/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 9/5/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/18/2023 Approved OSVALDO PARAMO
Shower Pan 10/18/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 12/15/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 12/15/2023 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/29/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 12/29/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 12/29/2023 Approved ALIZAH MAYAGOITIA
Final 1/16/2024 Corrections Issued OSVALDO PARAMO
Green Building Final 1/16/2024 Approved OSVALDO PARAMO
Service/Power Release 1/16/2024 Approved OSVALDO PARAMO
Smoke Detectors 1/16/2024 Approved OSVALDO PARAMO
Final 1/22/2024 OK to Issue CofO OSVALDO PARAMO