5417 1/2 E BALTIMORE ST 90042
Certificate Information: 5417 1/2 E BALTIMORE ST 90042
- Application / Permit
- 23016-10000-02234
- Plan Check / Job No.
- B23LA01352
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) laundry room, storage room, and garage to ADU per WFPP and CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/29/2023
- Issuing Office
- Current Status
- CofO Issued on 4/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | JASON JANGADA |
| Corrections Issued | 2/20/2023 | JASON JANGADA |
| Applicant returned to address corrections | 10/4/2023 | AMY GUEVARRA |
| Plan Check Approved | 10/25/2023 | AMY GUEVARRA |
| Issued | 10/29/2023 | APPLICANT |
| CofO in Progress | 4/21/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/26/2025 | DEROLD HAUFF |
| CofO Issued | 4/26/2025 | DEROLD HAUFF |
| Permit Finaled | 4/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/3/2023 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 3/17/2023 | CINDY QI |
| Sewer availability | Cleared | 3/17/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2023 | CINDY QI |
| Grading Pre-Inspection | Cleared | 6/21/2023 | SERGIO VALENZUELA |
| Construction near power lines | Cleared | 8/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | West Coast Rivers Construction Co; Lic. No.: 892174-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2023 | No Access for Inspection | ROY SPAULDING |
| Underground Mechanical | 12/8/2023 | No Access for Inspection | ROY SPAULDING |
| Wood Frame | 12/8/2023 | No Access for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 12/12/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 12/12/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 2/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 2/27/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 2/27/2024 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 2/27/2024 | Approved | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 2/27/2024 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 3/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/21/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/26/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 6/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 6/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 11/8/2024 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 12/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/16/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/23/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 12/23/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 12/23/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 12/23/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 12/23/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 12/31/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 12/31/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 12/31/2024 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 12/31/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | CRAIG DAVIS |
| Final | 1/21/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 1/21/2025 | No Access for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Ready | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | OSVALDO PARAMO |
| Final | 1/27/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 1/27/2025 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | OSVALDO PARAMO |
| Final | 2/3/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 2/14/2025 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 2/14/2025 | Approved | CRAIG DAVIS |
| Service/Power Release | 2/14/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 2/21/2025 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/27/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/12/2025 | Approved | DAVID WILLIAMS |
| Gas Test | 3/12/2025 | Approved | DAVID WILLIAMS |
| Final | 4/21/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |