12005 S AVALON BLVD 108 90061

Certificate Information: 12005 S AVALON BLVD 108 90061

Application / Permit
23016-10000-01788
Plan Check / Job No.
B23LA01063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Ice Cream Parlor
Work Description
Change of use from Retail to Ice Cream Parlor. Hours of operation will be from 7:00 am to 11:00 pm.
Permit Issued
Issued on 4/4/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 SALVADOR QUINTANILLA
Corrections Issued 1/26/2023 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/14/2023 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/28/2023 SALVADOR QUINTANILLA
Plan Check Approved 3/23/2023 SALVADOR QUINTANILLA
Issued 4/4/2023 APPLICANT
CofO in Progress 4/17/2024 ALFREDO LOPEZ
CofO Issued 4/17/2024 ERNESTO CORRAL
Permit Finaled 4/17/2024 ERNESTO CORRAL

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 2/16/2023 ANACANY HURTADO
Miscellaneous Cleared 2/16/2023 ANACANY HURTADO
ZA Case Cleared 2/16/2023 ANACANY HURTADO
ZA Case Cleared 2/16/2023 ANACANY HURTADO
Food Service Establishment Cleared 2/21/2023 PAWAN VERMA
Food establishment approval Cleared 2/28/2023 LACDHS APPROVED
Eng Process Fee Ord 176,300 Cleared 3/1/2023 ANA SORIANO
Sewer availability Cleared 3/1/2023 ANA SORIANO
Community Plan Implem. Overlay Cleared 3/14/2023 HELEN JADALI

Contact Information

Contractor Lujan And Associates; Lic. No.: 963892-B 7737 OTTO STREET      DOWNEY, CA 90240

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 4/5/2023 Partial Approval ALAN MORELOS
Drywall Nailing 4/6/2023 Partial Approval ALAN MORELOS
Drywall Nailing 4/17/2023 Approved ALAN MORELOS
Final 7/7/2023 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved ALAN MORELOS
Smoke Detectors 7/7/2023 Approved ALAN MORELOS
Final 7/14/2023 Conditional Approval DARRYL ARNOLD