826 W COLDEN AVE 1-7 90044
Certificate Information: 826 W COLDEN AVE 1-7 90044
- Application / Permit
- 23016-10000-01607
- Plan Check / Job No.
- B23LA00960
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERSION OF (E) STORAGE ROOM ON SECOND FLOOR OF (E) 6 UNIT APT. INTO ONE ADU PER STATE LAW AND GCS6585.2(e)(1)(C).(SEE COMMENTS).
- Permit Issued
- Issued on 4/24/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2023 | ZAW HAN |
| Corrections Issued | 2/1/2023 | ZAW HAN |
| Building Plans Picked Up | 2/2/2023 | APPLICANT |
| Plan Check Approved | 3/14/2023 | SAMUEL GONZALEZ |
| Issued | 4/24/2023 | APPLICANT |
| CofO in Progress | 10/30/2023 | MARTIN TAVITIAN |
| CofO Issued | 11/14/2023 | ERNESTO CORRAL |
| Permit Finaled | 11/14/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2023 | STEVE MELGAR |
| Highway dedication | Cleared | 3/4/2023 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 3/4/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 3/4/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2023 | STEVE MELGAR |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2023 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 6/26/2023 | Approved | ALAN MORELOS |
| Wood Frame | 6/26/2023 | Approved | ALAN MORELOS |
| Drywall Nailing | 7/5/2023 | Approved | MARTIN TAVITIAN |
| T-Bar Ceiling | 7/11/2023 | No Access for Inspection | ALAN MORELOS |
| Final | 9/8/2023 | Conditional Approval | ALAN MORELOS |
| Green Building Final | 9/8/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 9/8/2023 | Approved | ALAN MORELOS |