2529-2529 1/2 S 3RD AVE 90018

Certificate Information: 2529-2529 1/2 S 3RD AVE 90018

Application / Permit
23016-10000-01467
Plan Check / Job No.
B23LA00905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Remodel of three unit apartment building to replace doors and windows. Remove exterior second door in each unit. Interior alteration to bathroom and kitchen of unit (2529 1/2). All exterior alterations per ADM-2021-5918-CWC.
Permit Issued
Issued on 6/28/2024
Issuing Office
West Los Angeles
Current Status
Issued on 6/28/2024

Permit Application Status History

Submitted 1/19/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 RICARDO RAMIREZ
Corrections Issued 1/19/2023 RICARDO RAMIREZ
Applicant returned to address corrections 5/24/2024 ZENA HADDIS
Plan Check Approved 6/17/2024 DAVID CASTILLO
Issued 6/28/2024 APPLICANT

Permit Application Clearance Information

HPOZ Cleared 1/19/2023 DEEPEAKA DHALIWAL
ZI Cleared 1/19/2023 DEEPEAKA DHALIWAL
Tenant Habitability Plan Cleared 1/4/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Palomino'S General Construction; Lic. No.: 709226-B 6370 RAHN AVENUE      LONG BEACH, CA 90805
Engineer Krakower,, Michael A; Lic. No.: S2443 160 WHITE OAK DR      ARCADIA, CA 91006

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 4/15/2025 Corrections Issued CHRISTOPHER BLACKWOOD
Wood Frame 4/23/2025 Partial Inspection MARTIN TAVITIAN
Insulation 11/24/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 5/14/2026 Partial Approval IAN BLINN
Interior/Exterior Lathing 5/14/2026 Partial Approval IAN BLINN
Wood Frame 5/14/2026 Partial Approval IAN BLINN
Interior/Exterior Lathing 5/22/2026 Partial Approval IAN BLINN
Drywall Nailing 6/2/2026 Partial Approval IAN BLINN
Interior/Exterior Lathing 6/10/2026 Partial Approval IAN BLINN