1713 W 247TH PL 90717

Certificate Information: 1713 W 247TH PL 90717

Application / Permit
23016-10000-01441
Plan Check / Job No.
B23LA00887
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan- INTERIOR REMODEL TO (E) SFD, CONVERT (E) STORAGE TO (N) KITCHEN , ENCLOSE 6'-4" X 14'-1" PORTION OF (E) COVERED PATIO TO CREATE (N) MASTER BEDROOM & CONVERT REMAINING 12'-1" X 23" (E) COVERED PATIO TO (N) TRELLIS
Permit Issued
Issued on 3/13/2023
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 ALEC MOUSAKHANIAN
Corrections Issued 2/10/2023 ALEC MOUSAKHANIAN
Plan Check Approved 3/11/2023 ALEC MOUSAKHANIAN
Issued 3/13/2023 APPLICANT
CofO in Progress 1/7/2026 EUGENE CASSIDY
Permit Finaled 1/8/2026 ANSON MAGLASANG
CofO Issued 1/8/2026 ANSON MAGLASANG
Permit Finaled 1/8/2026 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 2/21/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 2/23/2023 KHAING AYE
Roof/Waste drainage to street Cleared 2/28/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/21/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 7/3/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/12/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 7/29/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/29/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 7/29/2024 Corrections Issued EUGENE CASSIDY
METHANE-Rough 7/29/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 7/29/2024 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 8/1/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/9/2024 Approved EUGENE CASSIDY
HVAC-Rough 8/9/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/9/2024 Partial Approval EUGENE CASSIDY
Shower Pan 8/9/2024 Approved EUGENE CASSIDY
Insulation 8/14/2024 Approved EUGENE CASSIDY
Drywall Nailing 8/19/2024 Not Ready for Inspection BARRY HACHE
Drywall Nailing 10/8/2024 Approved EUGENE CASSIDY
Wood Frame 10/8/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/18/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/1/2025 Approved EUGENE CASSIDY
Final 12/1/2025 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 12/1/2025 Not Ready for Inspection EUGENE CASSIDY
Final 12/8/2025 Corrections Issued EUGENE CASSIDY
Smoke Detectors 12/8/2025 Not Ready for Inspection EUGENE CASSIDY
Final 12/18/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/18/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 1/7/2026 Approved EUGENE CASSIDY
Final 1/7/2026 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 1/7/2026 Approved EUGENE CASSIDY
PLUMBING-Final 1/7/2026 Approved EUGENE CASSIDY
Smoke Detectors 1/7/2026 Approved EUGENE CASSIDY