754 W 16TH ST A-C 90731
Certificate Information: 754 W 16TH ST A-C 90731
- Application / Permit
- 23016-10000-01363
- Plan Check / Job No.
- B22LA26889
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) 30'4" X 22'2" IRREGULARLY SHAPED STORAGE AND RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C). WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 1/29/2024
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | MADISON ODELL |
| Corrections Issued | 2/25/2023 | MADISON ODELL |
| Plan Check Approved | 4/12/2023 | DANIEL YIP |
| Issued | 1/29/2024 | APPLICANT |
| CofO in Progress | 9/17/2025 | JOSEPH MCGARRY |
| Permit Finaled | 9/18/2025 | ANSON MAGLASANG |
| CofO Issued | 9/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 9/18/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2023 | KHAING AYE |
| Sewer availability | Cleared | 4/10/2023 | KHAING AYE |
Contact Information
| Architect | Browning,, Jeffrey Carleton; Lic. No.: NA34782 | , |
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/3/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/3/2024 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 9/3/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/3/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/3/2025 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/3/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 3/28/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 4/2/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | JOSEPH MCGARRY |
| Final | 9/5/2025 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 9/5/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/16/2025 | Approved | JOSEPH MCGARRY |
| Final | 9/16/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| PLUMBING-Final | 9/16/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 9/16/2025 | Approved | JOSEPH MCGARRY |