3724 S VETERAN AVE 90034
Certificate Information: 3724 S VETERAN AVE 90034
- Application / Permit
- 23016-10000-01146
- Plan Check / Job No.
- B23LA00690
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL TWO (2) SCCS AND ONE WOOD SHEAR WALL
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/25/2024
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | VARAND SARKISIAN |
| Corrections Issued | 2/16/2023 | VARAND SARKISIAN |
| Quality Review Completed | 2/23/2023 | HANS SANTIAGO |
| Building Plans Picked Up | 5/24/2023 | APPLICANT |
| Plan Check Approved | 5/31/2023 | VARAND SARKISIAN |
| Issued | 7/25/2023 | APPLICANT |
| OK for CofC | 1/25/2024 | MICHAEL PETRUSKO |
| CofC Issued | 1/25/2024 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/10/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Basseri Engineering & Construction; Lic. No.: 724559-B | 5250 W CENTRY BLVD #300 LOS ANGELES, CA 90045 |
| Engineer | Basseri,, Siavash M; Lic. No.: C45487 | 5250 W CENTURY BLVD STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 8/29/2023 | Corrections Issued | FARHAD DADBIN |
| Footing/Foundation/Slab | 9/12/2023 | Partial Approval | FARHAD DADBIN |
| Deputy Steel/Welding | 10/6/2023 | Conditional Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 10/31/2023 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 10/31/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/2/2023 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 11/2/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 12/7/2023 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 12/28/2023 | Approved | FARHAD DADBIN |
| Final | 1/9/2024 | Partial Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 1/9/2024 | Approved | MICHAEL PETRUSKO |
| Final | 1/25/2024 | OK for CofC | MICHAEL PETRUSKO |