1141-1141 3/4 W 45TH ST 90037
Certificate Information: 1141-1141 3/4 W 45TH ST 90037
- Application / Permit
- 23016-10000-01122
- Plan Check / Job No.
- B23LA00679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT ATTACHED GARAGE INTO A.D.U. PER STATE LAW. REPAIR DUPLEX BREEZEWAY CONNECTION. "COMPLY WITH DEPARTMENT ORDER effective date 11/02/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | AUNG SOE |
| Corrections Issued | 1/23/2023 | AUNG SOE |
| Building Plans Picked Up | 1/24/2023 | APPLICANT |
| Applicant returned to address corrections | 3/13/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 5/22/2023 | DANIEL SMILEY |
| Plan Check Approved | 10/21/2024 | MINA HABILI |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 12/24/2025 | DANIEL GUEVARA |
| Permit Finaled | 4/6/2026 | CLAUDIO MORENO |
| CofO Issued | 4/6/2026 | CLAUDIO MORENO |
| Permit Finaled | 4/6/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2023 | JOSEPH RHYU |
| Sewer availability | Cleared | 6/29/2023 | JOSEPH RHYU |
| Senate Bill 9 | Cleared | 7/19/2023 | JASON CHAN |
| Community Plan Implem. Overlay | Cleared | 8/23/2023 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2023 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 6/20/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Ruiz Development & Enigneering; Lic. No.: 1120759-B | 10400 ROUSELLE DR JURUPA VALLEY, CA 91752 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2024 | Approved | DANIEL GUEVARA |
| Excavation/Setback/Form/Re-Bar | 12/23/2024 | Approved | DANIEL GUEVARA |
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Rough | 3/12/2025 | Approved | DANIEL GUEVARA |
| Gas Test | 3/12/2025 | Approved | DANIEL GUEVARA |
| HVAC-Rough | 3/12/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Rough | 3/12/2025 | Approved | DANIEL GUEVARA |
| Insulation | 3/21/2025 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 3/21/2025 | Approved | DANIEL GUEVARA |
| Drywall Nailing | 4/18/2025 | Approved | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | DANIEL GUEVARA |
| Shower Pan | 4/18/2025 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 5/5/2025 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Final | 9/15/2025 | Approved | DANIEL GUEVARA |
| Green Building Final | 9/15/2025 | Approved | DANIEL GUEVARA |
| HVAC-Final | 9/15/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Final | 9/15/2025 | Approved | DANIEL GUEVARA |
| Service/Power Release | 9/15/2025 | Approved | DANIEL GUEVARA |
| Smoke Detectors | 9/15/2025 | Approved | DANIEL GUEVARA |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | DANIEL GUEVARA |
| Final | 12/23/2025 | OK to Issue CofO | DANIEL GUEVARA |
| Green Building Rough | 12/23/2025 | Approved | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | DANIEL GUEVARA |