749 N VENDOME ST 90026
Certificate Information: 749 N VENDOME ST 90026
- Application / Permit
- 23016-10000-00930
- Plan Check / Job No.
- B23LA00575
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY SEISMIC REINFORCEMENT PER LABC CHAPTER 93 AT THE BUILDING PARKING GARAGE USING (3) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
- Permit Issued
- Issued on 6/1/2023
- Issuing Office
- Current Status
- CofC Issued on 1/26/2024
Permit Application Status History
| Submitted | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | HANS SANTIAGO |
| Corrections Issued | 2/13/2023 | HANS SANTIAGO |
| Quality Review Completed | 2/13/2023 | LIPING TENG |
| Applicant returned to address corrections | 2/23/2023 | HANS SANTIAGO |
| Plan Check Approved | 3/30/2023 | ANDREW SANTIAGO |
| Issued | 6/1/2023 | APPLICANT |
| OK for CofC | 11/1/2023 | JACOB MYERS |
| CofC Issued | 1/26/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/30/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | , |
| Contractor | Perluss Sheldon K; Lic. No.: 759817-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2023 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 7/24/2023 | Corrections Issued | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Approved | VAHE KELEDJIAN |
| Structural Steel Frame | 8/3/2023 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 8/3/2023 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 8/15/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Wood Frame | 8/17/2023 | Approved | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 10/10/2023 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | JACOB MYERS |
| Final | 11/1/2023 | OK for CofC | JACOB MYERS |
| METHANE-Final | 11/1/2023 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 11/1/2023 | Approved | JACOB MYERS |