10324-10326 W DUNKIRK AVE 90025

Certificate Information: 10324-10326 W DUNKIRK AVE 90025

Application / Permit
23016-10000-00855
Plan Check / Job No.
B23LA00527
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert existing 350 sf garage/utility room into ADU.PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/1/2023
Issuing Office
Current Status
CofO Issued on 7/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2023 APPLICANT
Assigned to Plan Check Engineer 1/20/2023 ALFREDO JARA
Corrections Issued 1/21/2023 ALFREDO JARA
Applicant returned to address corrections 2/9/2023 ALFREDO JARA
Applicant returned to address corrections 2/18/2023 ALFREDO JARA
Applicant returned to address corrections 2/24/2023 AMY GUEVARRA
Plan Check Approved 2/26/2023 ALFREDO JARA
Issued 3/1/2023 APPLICANT
CofO in Progress 6/28/2023 STEPHANIE SWANSON
CofO in Progress 6/28/2023 STEPHANIE SWANSON
Permit Finaled 7/3/2023 DANIEL ORRANTE
CofO Issued 7/3/2023 DANIEL ORRANTE
Permit Finaled 7/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/26/2023 JENSON LEE
Roof/Waste drainage to street Cleared 1/26/2023 JENSON LEE
Sewer availability Cleared 1/26/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 1/30/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 3/17/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 3/17/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 3/17/2023 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/30/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 3/30/2023 Approved STEPHANIE SWANSON
Final 3/30/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 3/30/2023 Approved STEPHANIE SWANSON
METHANE-Final 3/30/2023 Approved STEPHANIE SWANSON
METHANE-Rough 3/30/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 3/30/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 3/30/2023 Approved STEPHANIE SWANSON
Final 4/13/2023 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 5/1/2023 Corrections Issued STEPHANIE SWANSON
Final 6/28/2023 OK to Issue CofO STEPHANIE SWANSON