11151 W MISSOURI AVE 90025
Certificate Information: 11151 W MISSOURI AVE 90025
- Application / Permit
- 23016-10000-00847
- Plan Check / Job No.
- B23LA00521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Shooting Range
- Work Description
- CHANGE OF USE FROM OFFICE TO INDOOR SHOOTING RANGE
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 2/2/2023 | APPLICANT |
| Corrections Issued | 2/16/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/21/2023 | KEN GILL |
| Building Plans Picked Up | 2/22/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 4/14/2023 | APPLICANT |
| Plan Check Approved | 6/12/2023 | ARSALAN SHABESTARI |
| Issued | 6/12/2023 | APPLICANT |
| CofO in Progress | 12/26/2023 | PAUL DAVIDSON |
| Permit Finaled | 12/26/2023 | DAVID TSAU |
| CofO Issued | 12/26/2023 | DAVID TSAU |
| Permit Finaled | 12/26/2023 | DAVID TSAU |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/30/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | JASON NG |
| ZA Case | Cleared | 4/4/2023 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 4/7/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 5/9/2023 | FREDDY GARCIA |
| DAS Clearance | Cleared | 5/26/2023 | ARSALAN SHABESTARI |
| Green Code | Cleared | 6/9/2023 | MICHAEL MARTINEZ |
Contact Information
| Contractor | Caisteal Builders Inc; Lic. No.: 800578-B | 3910 E CORONADO ST #101 ANAHEIM, CA 92807 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 6/22/2023 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Masonry | 6/23/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Masonry Wall/Backfill | 6/26/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 6/27/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 6/28/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 6/29/2023 | Conditional Approval | PAUL DAVIDSON |
| Masonry Wall/Backfill | 6/30/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 7/5/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/5/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 8/1/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 8/2/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 8/22/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 8/22/2023 | Partial Approval | PAUL DAVIDSON |
| Masonry Wall/Backfill | 9/7/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 9/8/2023 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 9/11/2023 | Partial Approval | PAUL DAVIDSON |
| Insulation | 9/13/2023 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 9/25/2023 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 9/27/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 9/27/2023 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 10/10/2023 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 10/20/2023 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 10/20/2023 | Partial Inspection | CASIMIR BRITTON |
| Deputy Reinf. Masonry | 10/26/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 10/26/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 10/27/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Masonry Wall/Backfill | 10/31/2023 | Approved | PAUL DAVIDSON |
| Partition/T-Bar Ceiling | 12/7/2023 | Approved | MICHAEL PETRUSKO |
| Final | 12/20/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 12/20/2023 | Approved | PAUL DAVIDSON |
| Green Building Rough | 12/20/2023 | Approved | PAUL DAVIDSON |
| METHANE-Final | 12/20/2023 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 12/20/2023 | Approved | PAUL DAVIDSON |
| Reinforced Masonry Frame | 12/20/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 12/20/2023 | Approved | PAUL DAVIDSON |
| Final | 12/21/2023 | OK to Issue CofO | PAUL DAVIDSON |