3759 S VINTON AVE 90034
Certificate Information: 3759 S VINTON AVE 90034
- Application / Permit
- 23016-10000-00834
- Plan Check / Job No.
- B23LA00502
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install One Cantilever Column and Four Hardy Frame Shear Walls
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- CofC Issued on 7/27/2023
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | HANS SANTIAGO |
| Corrections Issued | 1/23/2023 | HANS SANTIAGO |
| Quality Review Completed | 1/24/2023 | LIPING TENG |
| Plan Check Approved | 2/9/2023 | ANDREW SANTIAGO |
| Issued | 5/10/2023 | APPLICANT |
| OK for CofC | 7/12/2023 | MICHAEL PETRUSKO |
| CofC Issued | 7/27/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/26/2023 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 2/21/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Xebec Construction; Lic. No.: 638225-B | 1460 7TH STREET SUITE 203 SANTA MONICA, CA 90401 |
| Engineer | Namdar,, Mansour; Lic. No.: NA2976 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 5/19/2023 | Approved | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 6/15/2023 | Approved | MICHAEL PETRUSKO |
| Insulation | 6/15/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 6/15/2023 | Approved | MICHAEL PETRUSKO |
| Deputy Steel/Welding | 6/16/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Reinf. Concrete | 6/20/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Approved | MICHAEL PETRUSKO |
| Structural Steel Frame | 6/22/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 6/22/2023 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 6/28/2023 | Approved | MICHAEL PETRUSKO |
| Final | 7/12/2023 | OK for CofC | MICHAEL PETRUSKO |
| METHANE-Final | 7/12/2023 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Approved | MICHAEL PETRUSKO |