5716 W SATURN ST 90019

Certificate Information: 5716 W SATURN ST 90019

Application / Permit
23016-10000-00718
Plan Check / Job No.
B23LA00398
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A) . Work per Engineered design .
Permit Issued
Issued on 7/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2023 APPLICANT
Assigned to Plan Check Engineer 1/16/2023 VICTOR CHEN
Corrections Issued 1/17/2023 VICTOR CHEN
Building Plans Picked Up 1/20/2023 APPLICANT
Plan Check Approved 7/20/2023 GEORGE ALVAREZ
Issued 7/20/2023 APPLICANT
CofO in Progress 8/12/2024 STUART CHAPMAN
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/26/2023 JEREMY CHOK
Roof/Waste drainage to street Cleared 1/26/2023 JEREMY CHOK
Sewer availability Cleared 1/26/2023 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 1/27/2023 JEREMY CHOK
Construction near power lines Cleared 5/26/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chiang,, Tzuu Pien; Lic. No.: C72618 18295 AGUIRO STREET      ROWLAND HEIGHTS, CA 91748

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 8/31/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 9/1/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Conditional Approval JOSE AVILA
PLUMBING-Rough 9/12/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 9/19/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 9/19/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 9/25/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 9/25/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 9/27/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 9/27/2023 Approved JOSE AVILA
HVAC-Rough 10/2/2023 Approved JOSE AVILA
Wood Frame 10/2/2023 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 10/5/2023 Approved Pending GreenApproval JOSE AVILA
Green Building Rough 10/5/2023 Approved JOSE AVILA
METHANE-Rough 10/5/2023 Approved JOSE AVILA
Drywall Nailing 10/12/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/12/2023 Partial Approval STUART CHAPMAN
Shower Pan 10/12/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/24/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 2/16/2024 Approved STUART CHAPMAN
Final 2/16/2024 Corrections Issued STUART CHAPMAN
Green Building Final 2/16/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 2/16/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 2/22/2024 Approved STUART CHAPMAN
Final 2/22/2024 Corrections Issued STUART CHAPMAN
HVAC-Final 2/22/2024 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 2/22/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 8/12/2024 Approved STUART CHAPMAN
Final 8/12/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/12/2024 Approved STUART CHAPMAN