1545 W 41ST PL 90062

Certificate Information: 1545 W 41ST PL 90062

Application / Permit
23016-10000-00674
Plan Check / Job No.
B23LA00389
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-3" x 18'-5" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT WITH ADDITION OF 7'-10" x 20'-3" PER LAMC 12.22 A.33(c) AND (d) .WORK DONE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 12/01/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/10/2024
Issuing Office
Current Status
Issued on 7/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/13/2023 APPLICANT
Assigned to Plan Check Engineer 1/20/2023 MIROOSH KHACHATOORIAN
Corrections Issued 1/21/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/18/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 2/23/2023 MIROOSH KHACHATOORIAN
Issued 7/10/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/3/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/3/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/9/2023 TREVOR QUAN
Sewer availability Cleared 2/9/2023 TREVOR QUAN

Contact Information

Architect Bruce,, Thomas A; Lic. No.: C31251 1837 N WILTON PL 6      LOS ANGELES, CA 90028
Contractor Owner-Builder       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/12/2024 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/19/2024 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/6/2024 Approved JOHN PARKER
Pre-Inspection 6/25/2025 Corrections Issued JOHN PARKER
BUILDING-Rough-Frame 7/29/2025 Approved JOHN PARKER
ELECTRICAL-Rough 7/29/2025 Approved JOHN PARKER
Green Building Rough 7/29/2025 Approved JOHN PARKER
Drywall Nailing 9/23/2025 Partial Approval JOHN PARKER
HVAC-Rough 9/23/2025 Approved JOHN PARKER
Interior/Exterior Lathing 9/23/2025 Approved JOHN PARKER
PLUMBING-Rough 9/23/2025 Approved JOHN PARKER
Drywall Nailing 10/17/2025 Approved JOHN PARKER
ELECTRICAL-Rough 2/9/2026 Approved JOHN PARKER
Gas Test 2/9/2026 Approved JOHN PARKER
Underground Mechanical 2/9/2026 Approved JOHN PARKER
Final 4/8/2026 Not Ready for Inspection JOHN PARKER
Green Building Final 4/8/2026 Approved JOHN PARKER
Insulation 4/8/2026 Approved JOHN PARKER
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready JOHN PARKER
Shower Pan 4/8/2026 Approved JOHN PARKER
Smoke Detectors 4/8/2026 Approved JOHN PARKER
Final 4/17/2026 Partial Approval JOHN PARKER
SGSOV-Seismic Gas S/O Valve 4/17/2026 SGSOV Approved JOHN PARKER