557 N KENTER AVE 90049
Certificate Information: 557 N KENTER AVE 90049
- Application / Permit
- 23016-10000-00583
- Plan Check / Job No.
- B22LA26848
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- interior remodel to (E) sfd and Convert portion of garage to pantry and removel of portion of roof
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 7/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/22/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/14/2023 | MOHAMMAD ESMAILI |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 7/12/2024 | ARAM AVEDISIAN |
| Permit Finaled | 7/15/2024 | DANIEL ORRANTE |
| CofO Issued | 7/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | JENSON LEE |
| Miscellaneous | Cleared | 3/2/2023 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 3/4/2023 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | 1545 SAWTELLE BLVD STE 22 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2023 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/27/2023 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/31/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 8/8/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/8/2023 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 8/8/2023 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 8/10/2023 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/15/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/15/2023 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 8/23/2023 | Partial Inspection | ARAM AVEDISIAN |
| Insulation | 9/8/2023 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 9/20/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 9/21/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/27/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | ARAM AVEDISIAN |
| Final | 5/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/17/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 7/11/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 7/11/2024 | Approved | ARAM AVEDISIAN |
| Final | 7/12/2024 | OK to Issue CofO | ARAM AVEDISIAN |