1925 N PALMERSTON PL 1-7 90027
Certificate Information: 1925 N PALMERSTON PL 1-7 90027
- Application / Permit
- 23016-10000-00523
- Plan Check / Job No.
- B23LA00306
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) STORAGE ROOM INTO A.D.U. PER STATE LAW GCS65852.2(e)(1)(C) IN (E) APARTMENT.
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/17/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/27/2023 | APPLICANT |
| Applicant returned to address corrections | 5/16/2023 | ZAW HAN |
| Applicant returned to address corrections | 7/13/2023 | ZAW HAN |
| Applicant returned to address corrections | 7/18/2023 | MICHAEL LANZONE |
| Applicant returned to address corrections | 10/2/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 10/6/2023 | WEIJIAN HUANG |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 5/27/2025 | MARTIN TAVITIAN |
| CofO Issued | 5/27/2025 | ERNESTO CORRAL |
| Permit Finaled | 5/27/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2023 | WALLIE JONG |
| Sewer availability | Cleared | 2/14/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 9/28/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Elmers General Contractor Inc; Lic. No.: 883161-B | 7801 ENCINO AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Schaefer,, Jeffrey; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 1/8/2024 | Conditional Approval | RONALD JIMENEZ |
| Special/Order Compliance | 1/8/2024 | Corrections Issued | RONALD JIMENEZ |
| Interior/Exterior Lathing | 3/28/2024 | Partial Inspection | RAFAEL CORTES |
| Wood Frame | 3/28/2024 | Partial Approval | RAFAEL CORTES |
| Insulation | 4/2/2024 | Approved | RAFAEL CORTES |
| Wood Frame | 4/5/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 4/10/2024 | Approved | RAFAEL CORTES |
| Final | 4/8/2025 | OK to Issue CofO | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 4/8/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 4/8/2025 | Approved | MARTIN TAVITIAN |