1826 S VIRGINIA ROAD 90019

Certificate Information: 1826 S VIRGINIA ROAD 90019

Application / Permit
23016-10000-00481
Plan Check / Job No.
B22LA26839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 7'-1"X39' EXISTING COVERED BALCONY FOR BEDROOM EXTENSION AND REMODEL BEDROOMS AND BATHROOM AT SECOND FLOOR.
Permit Issued
Issued on 5/10/2024
Issuing Office
Current Status
CofO Issued on 10/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 DAWN MC NULTY
Corrections Issued 3/14/2023 DAWN MC NULTY
Quality Review Completed 3/22/2023 STEVEN KIM
Applicant returned to address corrections 2/23/2024 DAWN MC NULTY
Applicant returned to address corrections 4/18/2024 DAWN MC NULTY
Plan Check Approved 4/22/2024 DAWN MC NULTY
Issued 5/10/2024 APPLICANT
CofO in Progress 9/26/2024 JUSTIN HAWLEY
Permit Finaled 10/16/2024 RUBEN SALAS
CofO Issued 10/16/2024 RUBEN SALAS
Permit Finaled 10/16/2024 RUBEN SALAS

Permit Application Clearance Information

CPC Cleared 12/11/2023 DAMIAN GATTO
HPOZ Cleared 12/11/2023 DAMIAN GATTO
Miscellaneous Cleared 12/11/2023 DAMIAN GATTO
Miscellaneous Cleared 12/11/2023 DAMIAN GATTO
Miscellaneous Cleared 12/11/2023 DAMIAN GATTO
Sewer availability Cleared 4/1/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 4/2/2024 JUSTIN BICOL

Contact Information

Contractor Chief Top Remodeling Inc; Lic. No.: 1096793-B       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16000 VENTURA BLVD., PH 1203      ENCINO, CA 91436

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 7/9/2024 No Access for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 7/10/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 7/10/2024 Approved JUSTIN HAWLEY
Shower Pan 7/16/2024 Approved JOSH MEISTER
Insulation 7/18/2024 Not Ready for Inspection DAVID FEILER
Wood Frame 7/18/2024 Corrections Issued DAVID FEILER
HVAC-Rough 7/26/2024 Approved JUSTIN HAWLEY
Insulation 7/26/2024 Approved JUSTIN HAWLEY
Wood Frame 7/26/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/5/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 9/19/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 9/19/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 9/19/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/19/2024 Approved JOAQUIN GREENOUGH
Green Building Final 9/19/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 9/19/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 9/19/2024 Approved JOAQUIN GREENOUGH
METHANE-Final 9/19/2024 Approved JOAQUIN GREENOUGH
METHANE-Rough 9/19/2024 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 9/19/2024 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/19/2024 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 9/19/2024 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/26/2024 Approved JUSTIN HAWLEY
Drywall Nailing 9/26/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 9/26/2024 Approved JUSTIN HAWLEY
Final 9/26/2024 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 9/26/2024 Approved JUSTIN HAWLEY
Green Building Rough 9/26/2024 Approved JUSTIN HAWLEY
HVAC-Final 9/26/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 9/26/2024 Approved JUSTIN HAWLEY
Smoke Detectors 9/26/2024 Approved JUSTIN HAWLEY