768 N TERRACE 49 90042

Certificate Information: 768 N TERRACE 49 90042

Application / Permit
23016-10000-00476
Plan Check / Job No.
B22LA26837
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 1. Convert existing 355 SQ FT basement to new Bedroom, . Remove and replace deck with stairs at main entry
Permit Issued
Issued on 8/8/2024
Issuing Office
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 VARAND SARKISIAN
Corrections Issued 1/31/2023 VARAND SARKISIAN
Quality Review Completed 2/8/2023 HANS SANTIAGO
Applicant returned to address corrections 6/27/2023 VARAND SARKISIAN
Applicant returned to address corrections 9/18/2023 VARAND SARKISIAN
Plan Check Approved 3/6/2024 VARAND SARKISIAN
Issued 8/8/2024 APPLICANT
CofO in Progress 11/13/2024 ALIZAH MAYAGOITIA
No Progress 11/23/2024 DEROLD HAUFF
CofO in Progress 11/23/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 6/29/2023 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 8/22/2023 JOSEPH RHYU
Sewer availability Cleared 8/22/2023 JOSEPH RHYU
Grading Pre-Inspection Cleared 1/10/2024 SERGIO VALENZUELA

Contact Information

Contractor Mondragon Construction; Lic. No.: 847728-B       ,
Engineer Zhang,, Yao; Lic. No.: NA74572       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/12/2024 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 9/12/2024 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 9/12/2024 Partial Approval OSVALDO PARAMO
Insulation 9/25/2024 Approved OSVALDO PARAMO
Wood Frame 9/25/2024 Approved OSVALDO PARAMO
Drywall Nailing 10/9/2024 Approved OSVALDO PARAMO
Final 10/31/2024 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/31/2024 Approved OSVALDO PARAMO
Final 11/12/2024 OK to Issue CofO ALIZAH MAYAGOITIA