2948 N TYBURN ST 90039
Certificate Information: 2948 N TYBURN ST 90039
- Application / Permit
- 23016-10000-00469
- Plan Check / Job No.
- B23LA00244
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED EXISTING 3-CAR GARAGE & SHOP TO BE CONVERTED TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | JOHNPAUL ISIP |
| Corrections Issued | 1/16/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 2/21/2023 | PINANK PATEL |
| Plan Check Approved | 3/30/2023 | PINANK PATEL |
| Issued | 4/24/2023 | APPLICANT |
| CofO in Progress | 2/20/2024 | HAMIK HARTOUNIAN |
| CofO in Progress | 2/21/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
| CofO Issued | 2/22/2024 | DEROLD HAUFF |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 1/27/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 1/27/2023 | AMAAN MALIK |
| ZI | Cleared | 2/1/2023 | MAYELA VILLA |
| Construction near power lines | Cleared | 3/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Quiaot,, Florentino V; Lic. No.: NA38659 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/22/2023 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 5/22/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/7/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/11/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/11/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/11/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/20/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 7/20/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/1/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/1/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/4/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/4/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/4/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/15/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/15/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/18/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/25/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/25/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/25/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/18/2023 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 9/18/2023 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/18/2023 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 10/2/2023 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/2/2023 | Partial Inspection | JOSEPH MCGARRY |
| Shower Pan | 10/2/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 10/5/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 10/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/1/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 2/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 2/1/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/1/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 2/15/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| HVAC-Final | 2/15/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 2/15/2024 | Not Required | HAMIK HARTOUNIAN |
| Final | 2/20/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |