2948 N TYBURN ST 90039

Certificate Information: 2948 N TYBURN ST 90039

Application / Permit
23016-10000-00469
Plan Check / Job No.
B23LA00244
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED EXISTING 3-CAR GARAGE & SHOP TO BE CONVERTED TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/24/2023
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2023 APPLICANT
Assigned to Plan Check Engineer 1/13/2023 JOHNPAUL ISIP
Corrections Issued 1/16/2023 JOHNPAUL ISIP
Applicant returned to address corrections 2/21/2023 PINANK PATEL
Plan Check Approved 3/30/2023 PINANK PATEL
Issued 4/24/2023 APPLICANT
CofO in Progress 2/20/2024 HAMIK HARTOUNIAN
CofO in Progress 2/21/2024 HAMIK HARTOUNIAN
Permit Finaled 2/22/2024 DEROLD HAUFF
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/27/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/27/2023 AMAAN MALIK
Sewer availability Cleared 1/27/2023 AMAAN MALIK
ZI Cleared 2/1/2023 MAYELA VILLA
Construction near power lines Cleared 3/27/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Quiaot,, Florentino V; Lic. No.: NA38659       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2023 Corrections Issued SCOTT FINNILA
Underground Mechanical 5/22/2023 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/25/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/25/2023 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/1/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/7/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/11/2023 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 7/11/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/11/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 7/11/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/20/2023 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 7/20/2023 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 8/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 8/1/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/4/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/4/2023 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 8/4/2023 Approved HAMIK HARTOUNIAN
Insulation 8/15/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/15/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/18/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/25/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/25/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 8/25/2023 Approved HAMIK HARTOUNIAN
Insulation 8/25/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/18/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Approved BRIAN SULLIVAN
Insulation 9/18/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 9/18/2023 Corrections Issued BRIAN SULLIVAN
Drywall Nailing 10/2/2023 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 10/2/2023 Partial Inspection JOSEPH MCGARRY
Shower Pan 10/2/2023 Not Ready for Inspection JOSEPH MCGARRY
Shower Pan 10/5/2023 Approved HAMIK HARTOUNIAN
HVAC-Final 10/26/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/1/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/1/2024 Approved HAMIK HARTOUNIAN
Final 2/1/2024 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 2/1/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/1/2024 Approved HAMIK HARTOUNIAN
Final 2/15/2024 OK to Issue CofO HAMIK HARTOUNIAN
HVAC-Final 2/15/2024 Approved HAMIK HARTOUNIAN
Service/Power Release 2/15/2024 Not Required HAMIK HARTOUNIAN
Final 2/20/2024 OK to Issue CofO HAMIK HARTOUNIAN