189 S THE GROVE DR K2 90036
Certificate Information: 189 S THE GROVE DR K2 90036
- Application / Permit
- 23016-10000-00455
- Plan Check / Job No.
- B23LA00227
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- ePlan ; CHANGE OF USE FROM TAKE OUT RESTAURANT TO COFEE SHOP
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Current Status
- Issued on 3/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/14/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/7/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/23/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/4/2023 | MOHAMMAD ESMAILI |
| Issued | 3/7/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | JEANIE LAM |
| Sewer availability | Cleared | 2/27/2023 | JEANIE LAM |
| "T" removal | Cleared | 3/3/2023 | MAXFIELD VERMY |
| Comm Cor/Mini-Mall | Cleared | 3/3/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 3/3/2023 | MAXFIELD VERMY |
| Food establishment approval | Cleared | 3/4/2023 | LACDHS APPROVED |
Contact Information
| Architect | 9322, Third Ave; Lic. No.: C38399 | #601 BROOKLYN, NY 11209 |
| Contractor | J P Addison Construction Inc; Lic. No.: 1029562-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 4/20/2023 | Partial Inspection | ALFREDO LOPEZ |
| METHANE-Final | 4/20/2023 | Approved | ALFREDO LOPEZ |
| METHANE-Rough | 4/20/2023 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 4/20/2023 | Approved | ALFREDO LOPEZ |
| Wood Frame | 4/20/2023 | Approved | ALFREDO LOPEZ |
| Final | 4/21/2023 | Conditional Approval | ALFREDO LOPEZ |
| Pre-Inspection | 4/24/2023 | Not Ready for Inspection | JEROME BLACKWOOD |