1177 1/2 E 41ST PL 90011
Certificate Information: 1177 1/2 E 41ST PL 90011
- Application / Permit
- 23016-10000-00340
- Plan Check / Job No.
- B23LA00137
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). (Two ADUs per State Law) All work per WFPP, NFPA-13D THRU OUT
- Permit Issued
- Issued on 3/31/2023
- Issuing Office
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2023 | VICTOR CHEN |
| Corrections Issued | 1/17/2023 | VICTOR CHEN |
| Building Plans Picked Up | 1/20/2023 | APPLICANT |
| Applicant returned to address corrections | 3/24/2023 | VICTOR CHEN |
| Plan Check Approved | 3/31/2023 | AUNG SOE |
| Issued | 3/31/2023 | APPLICANT |
| CofO in Progress | 6/20/2023 | BRENDAN MORELLI |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 3/7/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 3/7/2023 | SPENCER WEJROWSKI |
| Address approval | Cleared | 3/9/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | CINDY QI |
| Sewer availability | Cleared | 3/9/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/6/2023 | Partial Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/27/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 4/27/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 4/27/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 4/27/2023 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 4/27/2023 | Approved | BRENDAN MORELLI |
| Insulation | 5/4/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 5/4/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 5/15/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/15/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/7/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 6/7/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 6/7/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 6/7/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/13/2023 | Approved | BRENDAN MORELLI |
| Final | 6/13/2023 | OK to Issue CofO | BRENDAN MORELLI |