231 E 104TH ST 90003

Certificate Information: 231 E 104TH ST 90003

Application / Permit
23016-10000-00284
Plan Check / Job No.
B22LA26802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'x 20' GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d) .
Permit Issued
Issued on 6/15/2023
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/13/2023 MIROOSH KHACHATOORIAN
Corrections Issued 1/17/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/11/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 6/13/2023 GIOVANNY CHAVEZ
Issued 6/15/2023 APPLICANT
CofO in Progress 2/21/2024 JAMES CHAVEZ
Permit Finaled 2/22/2024 ANSON MAGLASANG
CofO Issued 2/22/2024 ANSON MAGLASANG
Permit Finaled 2/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/3/2023 AMAAN MALIK
Sewer availability Cleared 2/3/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 2/8/2023 AMAAN MALIK
Construction near power lines Cleared 6/5/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/24/2023 Conditional Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 8/25/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 8/25/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Corrections Issued JOHN KLARIN
Sewer 9/18/2023 Approved JOHN KLARIN
Underground Mechanical 9/18/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 9/25/2023 Approved JAMES CHAVEZ
Green Building Rough 9/25/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 9/25/2023 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 9/25/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 9/27/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 9/27/2023 Approved JOHN KLARIN
Green Building Rough 9/27/2023 Approved JOHN KLARIN
HVAC-Rough 9/27/2023 Approved JOHN KLARIN
PLUMBING-Rough 9/27/2023 Approved JOHN KLARIN
Insulation 10/12/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 10/13/2023 Approved JOHN KLARIN
Drywall Nailing 10/17/2023 Approved JOHN KLARIN
Final 1/12/2024 Corrections Issued JOHN KLARIN
Green Building Final 1/12/2024 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/12/2024 Approved JOHN KLARIN
Final 1/24/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 1/24/2024 Approved JAMES CHAVEZ
Final 2/7/2024 Corrections Issued JAMES CHAVEZ
Final 2/13/2024 OK to Issue CofO JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 2/13/2024 Approved JAMES CHAVEZ