324 N KIRBY ST 90042
Certificate Information: 324 N KIRBY ST 90042
- Application / Permit
- 23016-10000-00055
- Plan Check / Job No.
- B22LA26705
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 2-STORY AND GROUND FLOOR ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE. EXISTING GARAGE TO REMAIN. 1 OF 2
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Current Status
- Issued on 6/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | MICHAEL LOPEZ |
| Corrections Issued | 2/24/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 3/8/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/28/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/11/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 6/24/2024 | MICHAEL LOPEZ |
| Issued | 6/2/2025 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 3/4/2023 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 4/14/2023 | MATTHEW CRAIG |
| Address approval | Cleared | 5/3/2023 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 5/3/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/3/2023 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 5/11/2023 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2023 | CHRISTOPHER ROCHA |
| Stormwater Pollution Mitigatn | Cleared | 8/7/2023 | MITESH PATEL |
| Grading Pre-Inspection | Cleared | 8/11/2023 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | CHRISTOPHER ROCHA |
| GPI Written Notices | Cleared | 6/24/2024 | ROBERT HUGHES |
Contact Information
| Contractor | Fhs Construction Inc; Lic. No.: 1027487-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/20/2025 | Partial Approval | DAVID WILLIAMS |
| Underground Mechanical | 7/17/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 7/23/2025 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/23/2025 | Partial Approval | DAVID WILLIAMS |
| Sewer | 7/23/2025 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/30/2025 | Partial Approval | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | DAVID WILLIAMS |
| HVAC-Rough | 10/22/2025 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 10/22/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 10/23/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 10/23/2025 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 11/10/2025 | Approved | DAVID WILLIAMS |
| Deputy Steel/Welding | 11/12/2025 | Conditional Approval | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/26/2025 | Approved | DAVID WILLIAMS |
| Insulation | 12/18/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 12/18/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Shower Pan | 12/18/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Rough | 12/24/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 12/24/2025 | Approved | DAVID WILLIAMS |
| Insulation | 12/24/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 12/24/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 1/14/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/16/2026 | Approved | DAVID WILLIAMS |