1355 N SAN PABLO ST 90033

Certificate Information: 1355 N SAN PABLO ST 90033

Application / Permit
23016-10000-00018
Plan Check / Job No.
B22LA26668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Laboratory
Work Description
ePlan Replacement of non-rated doors with labeled doors; Installation of 1-hour rated tunnel construction in 2nd, 3rd and 4th floor exit corridors; installation of Smokeguard curtains in front of Ground, 2nd, 3rd, and 4th floor elevator doors; Installation of new code-compliant exit signage on Ground, 2nd, 3rd, and 4th floors.
Permit Issued
Issued on 6/7/2023
Issuing Office
Current Status
Permit Finaled on 2/27/2025

Permit Application Status History

Submitted 1/8/2023 APPLICANT
Assigned to Plan Check Engineer 2/1/2023 MICHAEL LOPEZ
Corrections Issued 2/10/2023 MICHAEL LOPEZ
Quality Review Completed 2/21/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/17/2023 MICHAEL LOPEZ
Applicant returned to address corrections 5/11/2023 MICHAEL LOPEZ
Plan Check Approved 6/7/2023 MICHAEL LOPEZ
Issued 6/7/2023 APPLICANT
Permit Finaled 2/26/2025 RONALD JIMENEZ

Permit Application Clearance Information

Redevelopment Project Area Cleared 3/1/2023 GRACIELA ACOSTA
Fire Marshal Fire Life Safety Cleared 4/6/2023 ANDREW KO
Green Code Cleared 5/16/2023 AARON COSTA
DAS Clearance Cleared 5/18/2023 Hernan Arreola

Contact Information

Architect , ; Lic. No.: C34131       ,
Contractor Hamilton Healthcare Construction Inc; Lic. No.: 698100-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 6/28/2023 Approved JULIAN CAPUCETTI
Light Gage Steel Frame 6/28/2023 Approved JULIAN CAPUCETTI
Drywall Nailing 7/3/2023 Approved JULIAN CAPUCETTI
T-Bar Ceiling 7/20/2023 Conditional Approval JULIAN CAPUCETTI
Light Gage Steel Frame 8/22/2023 Partial Approval JULIAN CAPUCETTI
Final 7/9/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 7/9/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 7/9/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 2/26/2025 Permit Finaled RONALD JIMENEZ
Green Building Final 2/26/2025 Approved RONALD JIMENEZ
Smoke Detectors 2/26/2025 Approved RONALD JIMENEZ