103 N HARVARD BLVD 90004

Certificate Information: 103 N HARVARD BLVD 90004

Application / Permit
23014-70000-04409
Plan Check / Job No.
B23SL00093
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of dwelling to enlarge bedroom. Interior alteration to bathroom to create additional bathroom. Remodle kitchen to add laundry area. New uncovered deck in rear of dwelling.
Permit Issued
Issued on 11/2/2023
Issuing Office
South Los Angeles
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 RICARDO RAMIREZ
Corrections Issued 10/26/2023 RICARDO RAMIREZ
Plan Check Approved 11/2/2023 RICARDO RAMIREZ
Issued 11/2/2023 APPLICANT
CofO in Progress 10/15/2024 WILLIAM MICHALAK
Permit Finaled 3/6/2025 CLAUDIO MORENO
CofO Issued 3/6/2025 CLAUDIO MORENO
Permit Finaled 3/6/2025 CLAUDIO MORENO

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/31/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/2/2023 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/6/2023 No Access for Inspection JEFFREY MEAD
Pre-Inspection 11/8/2023 Approved KIM DOEPPING
Deputy Drilled-In Anchors 11/21/2023 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 11/27/2023 Corrections Issued WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 11/27/2023 Approved WILLIAM MICHALAK
Insulation 11/27/2023 Approved WILLIAM MICHALAK
PLUMBING-Rough 11/27/2023 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 12/4/2023 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 1/19/2024 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Rough 1/19/2024 Partial Approval WILLIAM MICHALAK
Green Building Rough 1/19/2024 Not Ready for Inspection WILLIAM MICHALAK
Insulation 1/19/2024 Approved WILLIAM MICHALAK
Drywall Nailing 1/26/2024 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 1/26/2024 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 7/16/2024 Approved WILLIAM MICHALAK
Final 7/16/2024 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 7/16/2024 Approved WILLIAM MICHALAK
Green Building Final 7/16/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 7/16/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 7/16/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 7/23/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 7/23/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 7/23/2024 Approved WILLIAM MICHALAK
Final 7/26/2024 Corrections Issued WILLIAM MICHALAK
Green Building Final 7/26/2024 Approved WILLIAM MICHALAK
Final 8/2/2024 OK to Issue CofO WILLIAM MICHALAK