145 1/2 E 60TH ST 90003

Certificate Information: 145 1/2 E 60TH ST 90003

Application / Permit
23014-70000-03063
Plan Check / Job No.
B23SL00033
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert and add to (e) garage to create ADU PER LAMC 12.22 A.33(c) AND (d). Demolish portion of existing covered breezeway (50sf) connecting dwelling to garage. Remaining to become attached patio (49sf) for ADU.
Permit Issued
Issued on 8/22/2023
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/1/2023 RICARDO RAMIREZ
Corrections Issued 8/2/2023 RICARDO RAMIREZ
Building Plans Picked Up 8/3/2023 APPLICANT
Plan Check Approved 8/17/2023 RICARDO RAMIREZ
Issued 8/22/2023 APPLICANT
CofO in Progress 6/5/2024 ALEJANDRO DE ARTOLA
Permit Finaled 6/11/2024 DEROLD HAUFF
CofO Issued 6/11/2024 DEROLD HAUFF
Permit Finaled 6/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 8/14/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/15/2023 CHRISTINA BRACO
Sewer availability Cleared 8/15/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/4/2023 Partial Approval ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 10/5/2023 Approved ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 10/12/2023 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/13/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/13/2023 Approved STUART CHAPMAN
PLUMBING-Rough 10/13/2023 Corrections Issued STUART CHAPMAN
Sewer 10/13/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/18/2023 Corrections Issued STUART CHAPMAN
Insulation 10/18/2023 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 10/18/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/26/2023 Corrections Issued ENRIQUE MIRELES
Green Building Rough 10/26/2023 Not Ready for Inspection ENRIQUE MIRELES
Insulation 10/26/2023 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 10/30/2023 Corrections Issued ENRIQUE MIRELES
Green Building Rough 10/30/2023 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 11/3/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 11/3/2023 Approved STUART CHAPMAN
HVAC-Rough 11/3/2023 Approved STUART CHAPMAN
Insulation 11/3/2023 Approved STUART CHAPMAN
Drywall Nailing 11/13/2023 Partial Approval JOSH MEISTER
Drywall Nailing 11/20/2023 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/27/2023 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 1/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/25/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 2/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 2/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/1/2024 Not Ready for Inspection SABAS ALONSO
Final 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/29/2024 Approved ALEJANDRO DE ARTOLA
Final 4/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/29/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/29/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/15/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/15/2024 Approved ALEJANDRO DE ARTOLA
Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 5/16/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/29/2024 Approved ALEJANDRO DE ARTOLA
Final 5/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/29/2024 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/29/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/29/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/29/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Final 6/4/2024 OK to Issue CofO ALEJANDRO DE ARTOLA