1725 W GRENADIER DR 90732
Certificate Information: 1725 W GRENADIER DR 90732
- Application / Permit
- 23014-40000-04903
- Plan Check / Job No.
- B23SP00256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED LIVING ROOM, MASTER BEDROOM, MASTER BATHROOM AND CLOSET ADDITION AT REAR OF (E) SFD WITH GARAGE.
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- San Pedro
- Current Status
- Issued on 6/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/7/2023 | LAWRENCE QUIRANTE |
| Quality Review Completed | 12/11/2023 | JOHN FRANCIA |
| Plan Check Approved | 5/14/2024 | LAWRENCE QUIRANTE |
| Issued | 6/13/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/9/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2024 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 3/5/2024 | AL GAMBLE |
| Construction near power lines | Cleared | 4/26/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Crisfield Construction; Lic. No.: 1054389-B | 1850 W 144TH ST GARDENA, CA 90249 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/2/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/15/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/15/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 7/17/2024 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 8/9/2024 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/9/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 10/2/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/2/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/2/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/2/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/2/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/10/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 10/10/2024 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 10/17/2024 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 10/17/2024 | Conditional Approval | JOSEPH MCGARRY |
| Shower Pan | 2/6/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/10/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/14/2025 | Approved | JOSEPH MCGARRY |