3613 S PARKER ST 90731

Certificate Information: 3613 S PARKER ST 90731

Application / Permit
23014-40000-04721
Plan Check / Job No.
B23SP00246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 6'-6" X 30' LIVING ROOM AND BATHROOM ADDITION AT REAR OF (E) SFD WITH GARAGE, PER WOOD FRAME PRESCRIPTIVE PROVISIONS (WFPP).
Permit Issued
Issued on 2/6/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/29/2023 LAWRENCE QUIRANTE
Corrections Issued 12/2/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 12/7/2023 APPLICANT
Applicant returned to address corrections 12/21/2023 SERGIO SILVA
Applicant returned to address corrections 1/4/2024 SERGIO SILVA
Plan Check Approved 2/1/2024 SERGIO SILVA
Issued 2/6/2024 APPLICANT
CofO in Progress 8/28/2024 EUGENE CASSIDY
Permit Finaled 8/30/2024 ANSON MAGLASANG
CofO Issued 8/30/2024 ANSON MAGLASANG
Permit Finaled 8/30/2024 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/13/2023 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 12/18/2023 KHAING AYE
Roof/Waste drainage to street Cleared 12/18/2023 KHAING AYE
Coastal Zone Cleared 1/22/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2024 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 6/12/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 6/13/2024 Approved JAMES CHAVEZ
Deputy Drilled-In Anchors 6/24/2024 Conditional Approval ANSON MAGLASANG
PLUMBING-Rough 6/25/2024 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/27/2024 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 7/12/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 7/12/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval JAMES CHAVEZ
Green Building Rough 7/12/2024 Approved JAMES CHAVEZ
HVAC-Rough 7/12/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 7/12/2024 Approved JAMES CHAVEZ
Insulation 7/16/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/16/2024 Partial Approval EUGENE CASSIDY
Drywall Nailing 7/17/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/17/2024 Approved EUGENE CASSIDY
Shower Pan 7/17/2024 Approved EUGENE CASSIDY
Final 8/14/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 8/14/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/14/2024 Not Required EUGENE CASSIDY
Smoke Detectors 8/14/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/27/2024 Approved EUGENE CASSIDY
Final 8/27/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/27/2024 Approved EUGENE CASSIDY
HVAC-Final 8/27/2024 Approved EUGENE CASSIDY
PLUMBING-Final 8/27/2024 Approved EUGENE CASSIDY