1253 W 26TH PL 90731

Certificate Information: 1253 W 26TH PL 90731

Application / Permit
23014-40000-03786
Plan Check / Job No.
B23SP00199
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED PATIO, BEDROOM AND BATHROOM ADDITIONS AT REAR OF (E) SFD.
Permit Issued
Issued on 4/23/2024
Issuing Office
San Pedro
Current Status
Issued on 4/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 LAWRENCE QUIRANTE
Corrections Issued 9/26/2023 LAWRENCE QUIRANTE
Quality Review Completed 9/26/2023 JOHN FRANCIA
Building Plans Picked Up 9/26/2023 APPLICANT
Applicant returned to address corrections 10/18/2023 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/31/2023 LAWRENCE QUIRANTE
Plan Check Approved 12/19/2023 LAWRENCE QUIRANTE
Issued 4/23/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/3/2023 KHAING AYE
Roof/Waste drainage to street Cleared 10/3/2023 KHAING AYE
Sewer availability Cleared 10/3/2023 KHAING AYE
Grading Pre-Inspection Cleared 12/8/2023 ROBERT HUGHES
Coastal Zone Cleared 12/13/2023 JOE TAM

Contact Information

Contractor Agrusa General Contracting; Lic. No.: 972732-B 1043 W 12TH STREET #3      SAN PEDRO, CA 90731
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2024 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 5/14/2024 Approved ANSON MAGLASANG
Footing/Foundation/Slab 5/14/2024 Approved ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 10/23/2024 Approved JOSEPH MCGARRY
Deputy Wood Construction 10/24/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/1/2024 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/1/2024 Approved JOSEPH MCGARRY
Green Building Rough 11/1/2024 Approved JOSEPH MCGARRY
HVAC-Rough 11/1/2024 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 11/1/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/14/2024 Approved JOSEPH MCGARRY
Insulation 11/14/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/14/2024 Partial Approval JOSEPH MCGARRY
Shower Pan 11/14/2024 Approved JOSEPH MCGARRY
Drywall Nailing 11/21/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/15/2025 Approved JOSEPH MCGARRY
Gas Test 2/21/2025 Approved JOSEPH MCGARRY
Final 8/7/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 8/7/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 8/7/2025 Approved EUGENE CASSIDY