1239 W 26TH PL 90731
Certificate Information: 1239 W 26TH PL 90731
- Application / Permit
- 23014-40000-03161
- Plan Check / Job No.
- B23SP00169
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED REMODEL AND ADDITION AT REAR OF (E) SFD.
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/13/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/22/2023 | APPLICANT |
| Applicant returned to address corrections | 11/14/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 1/30/2024 | LAWRENCE QUIRANTE |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 1/8/2025 | JOSEPH MCGARRY |
| Permit Finaled | 1/9/2025 | ANSON MAGLASANG |
| CofO Issued | 1/9/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/9/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/12/2023 | AL GAMBLE |
| Roof/Waste drainage to street | Cleared | 10/26/2023 | KHAING AYE |
| Sewer availability | Cleared | 10/26/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | KHAING AYE |
| Construction near power lines | Cleared | 12/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Agrusa General Contracting; Lic. No.: 972732-B | 1043 W 12TH STREET #3 SAN PEDRO, CA 90731 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 3/1/2024 | Corrections Issued | JAMES CHAVEZ |
| Reinforced Concrete Frame | 3/1/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 3/13/2024 | Conditional Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 3/29/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Partial Approval | JAMES CHAVEZ |
| Underground Mechanical | 4/30/2024 | Partial Approval | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 5/3/2024 | Conditional Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/14/2024 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 5/14/2024 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 5/14/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 5/14/2024 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 5/14/2024 | Partial Approval | ANSON MAGLASANG |
| Insulation | 5/20/2024 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/11/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/11/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 6/11/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 6/11/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/3/2024 | Approved | EUGENE CASSIDY |
| Insulation | 7/3/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/3/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 7/3/2024 | Approved | EUGENE CASSIDY |
| Final | 11/21/2024 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/21/2024 | Approved | JOSEPH MCGARRY |
| Green Building Final | 11/21/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 11/21/2024 | Approved | JOSEPH MCGARRY |
| Final | 1/8/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/8/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 1/8/2025 | Approved | JOSEPH MCGARRY |