10304 S GRAMERCY PL 90047

Certificate Information: 10304 S GRAMERCY PL 90047

Application / Permit
23014-40000-02795
Plan Check / Job No.
B23SP00145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/10/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 SERGIO SILVA
Corrections Issued 7/13/2023 SERGIO SILVA
Applicant returned to address corrections 8/3/2023 SERGIO SILVA
Plan Check Approved 8/10/2023 SERGIO SILVA
Issued 8/10/2023 APPLICANT
CofO in Progress 2/20/2024 JOSE MACIAS
CofO Issued 5/17/2024 DEROLD HAUFF
Permit Finaled 5/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 7/25/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 7/25/2023 CELINA MORENO
Sewer availability Cleared 7/25/2023 CELINA MORENO
ZA Case Cleared 7/26/2023 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 8/2/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/12/2023 Conditional Approval MICHAEL LEWIS
Insulation 9/20/2023 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 9/20/2023 Partial Approval MICHAEL LEWIS
Wood Frame 9/20/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/27/2023 Corrections Issued ENRIQUE MIRELES
Green Building Rough 10/27/2023 Approved ENRIQUE MIRELES
METHANE-Rough 10/27/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/3/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/3/2023 Approved ENRIQUE MIRELES
Insulation 11/7/2023 Approved ENRIQUE MIRELES
Drywall Nailing 11/9/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/14/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 11/27/2023 Approved ENRIQUE MIRELES
Final 2/6/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/6/2024 Approved ENRIQUE MIRELES
Green Building Final 2/6/2024 Approved ENRIQUE MIRELES
METHANE-Barrier 2/6/2024 Approved ENRIQUE MIRELES
METHANE-Subgrade 2/6/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/6/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/6/2024 Approved ENRIQUE MIRELES
Service/Power Release 2/8/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/16/2024 Approved JOSE MACIAS
Final 2/16/2024 OK to Issue CofO JOSE MACIAS
HVAC-Final 2/16/2024 Approved JOSE MACIAS
PLUMBING-Final 2/16/2024 Approved JOSE MACIAS