1922 N ROSEGLEN AVE 90731
Certificate Information: 1922 N ROSEGLEN AVE 90731
- Application / Permit
- 23014-40000-02489
- Plan Check / Job No.
- B23SP00127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED DINING ROOM AND KITCHEN AREA ADDITIONS ALONG SOUTHERLY EDGE OF BLDG.
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/29/2023 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/27/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 8/1/2023 | LAWRENCE QUIRANTE |
| Plan Check Approved | 8/24/2023 | SERGIO SILVA |
| Issued | 12/17/2024 | APPLICANT |
| CofO in Progress | 12/18/2025 | JOSEPH MCGARRY |
| Permit Finaled | 12/18/2025 | ANSON MAGLASANG |
| CofO Issued | 12/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/18/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2023 | MATTHEW JENKINS |
| Roof/Waste drainage to street | Cleared | 8/4/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tiongco,, John Lazarraga; Lic. No.: C70915 | 17715 CANEHILL AVE BELLFLOWER, CA 90706 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/26/2024 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/26/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/29/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/29/2025 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 1/29/2025 | Approved | BEN MOLSTAD |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 1/29/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/31/2025 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 1/31/2025 | Approved | BEN MOLSTAD |
| Deputy Wood Construction | 2/3/2025 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/4/2025 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 2/4/2025 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 2/4/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 2/13/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Wood Construction | 2/19/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 2/19/2025 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 2/21/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/26/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | JOSEPH MCGARRY |
| Final | 10/27/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/27/2025 | Approved | JOSEPH MCGARRY |
| Green Building Final | 10/27/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 10/27/2025 | Approved | JOSEPH MCGARRY |
| Final | 12/17/2025 | OK to Issue CofO | JOSEPH MCGARRY |