1100 W ROBIDOUX ST 90744
Certificate Information: 1100 W ROBIDOUX ST 90744
- Application / Permit
- 23014-40000-02255
- Plan Check / Job No.
- B23SP00108
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT (E) DETACH GARAGE TO ADU PER LAMC 12.22 A.33 (c)(d) WORK DONE PER WFPP
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2023 | KHUONG TRUONG |
| Corrections Issued | 6/13/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 6/20/2023 | APPLICANT |
| Applicant returned to address corrections | 5/30/2024 | SERGIO SILVA |
| Plan Check Approved | 6/18/2024 | LAWRENCE QUIRANTE |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 5/5/2025 | EUGENE CASSIDY |
| Permit Finaled | 5/6/2025 | ANSON MAGLASANG |
| CofO Issued | 5/6/2025 | ANSON MAGLASANG |
| Permit Finaled | 5/6/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | ANA SORIANO |
| Sewer availability | Cleared | 7/27/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 4/16/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2024 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 8/6/2024 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Subgrade | 8/15/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/15/2024 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/16/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 10/16/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 10/24/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 10/24/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/1/2024 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 11/1/2024 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 11/13/2024 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 11/22/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/24/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/24/2025 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 1/24/2025 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 1/24/2025 | Approved | EUGENE CASSIDY |
| METHANE-Final | 1/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/24/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 1/24/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/21/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | EUGENE CASSIDY |
| Final | 4/15/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/15/2025 | Approved | EUGENE CASSIDY |
| METHANE-Final | 4/15/2025 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 4/15/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/15/2025 | Approved | EUGENE CASSIDY |
| Final | 4/28/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/5/2025 | Approved | EUGENE CASSIDY |
| Final | 5/5/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 5/5/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/5/2025 | Approved | EUGENE CASSIDY |