1118 W CRUCES ST 90744

Certificate Information: 1118 W CRUCES ST 90744

Application / Permit
23014-40000-02096
Plan Check / Job No.
B23SP00101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITIONS AND PATIO COVER TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. COMPLY WITH DEPARTMENT ORDER effective date 03/23/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 982641.
Permit Issued
Issued on 4/18/2024
Issuing Office
San Pedro
Current Status
Issued on 4/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 5/30/2023 LAWRENCE QUIRANTE
Corrections Issued 5/30/2023 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/21/2023 SERGIO SILVA
Plan Check Approved 1/4/2024 SERGIO SILVA
Issued 4/18/2024 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 12/4/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 12/11/2023 KHAING AYE
Sewer availability Cleared 12/11/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 12/12/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/21/2024 Approved BRIAN CHRISTIAN
Footing/Foundation/Slab 7/15/2024 Not Ready for Inspection BRIAN CHRISTIAN
METHANE-Barrier 7/15/2024 Approved BRIAN CHRISTIAN
METHANE-Rough 7/15/2024 Approved BRIAN CHRISTIAN
Footing/Foundation/Slab 9/20/2024 Conditional Approval PAUL REECE
METHANE-Subgrade 9/20/2024 Corrections Issued PAUL REECE
PLUMBING-Rough 10/9/2024 Approved PAUL REECE
Insulation 10/23/2024 Approved PAUL REECE
Deputy Drilled-In Anchors 11/6/2024 Conditional Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 11/12/2024 Approved PAUL REECE
Green Building Rough 11/12/2024 Approved PAUL REECE
ELECTRICAL-Rough 12/10/2024 Approved BRIAN CHRISTIAN
HVAC-Rough 12/10/2024 Approved BRIAN CHRISTIAN
PLUMBING-Rough 12/10/2024 Approved BRIAN CHRISTIAN
Shower Pan 12/10/2024 Approved BRIAN CHRISTIAN
Insulation 12/23/2024 Approved PAUL REECE
Drywall Nailing 12/30/2024 Approved PAUL REECE
Final 2/3/2026 Not Ready for Inspection KELLY WARNER
Footing/Foundation/Slab 2/3/2026 Approved KELLY WARNER
Green Building Final 2/3/2026 Approved KELLY WARNER
METHANE-Subgrade 2/3/2026 Approved KELLY WARNER
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Ready KELLY WARNER
Smoke Detectors 2/3/2026 Approved KELLY WARNER
Final 2/4/2026 Not Ready for Inspection KELLY WARNER
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved KELLY WARNER