712 W SHEPARD ST 90731

Certificate Information: 712 W SHEPARD ST 90731

Application / Permit
23014-40000-00621
Plan Check / Job No.
B23SP00027
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY DECK ADDITION TO EXISTING 2-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 5/11/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 11/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 SERGIO SILVA
Corrections Issued 2/16/2023 SERGIO SILVA
Applicant returned to address corrections 2/23/2023 SERGIO SILVA
Applicant returned to address corrections 5/2/2023 LAWRENCE QUIRANTE
Plan Check Approved 5/11/2023 SERGIO SILVA
Issued 5/11/2023 APPLICANT
CofO in Progress 11/27/2023 JAMES CHAVEZ
Permit Finaled 11/27/2023 ANSON MAGLASANG
CofO Issued 11/27/2023 ANSON MAGLASANG
Permit Finaled 11/27/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/16/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 2/16/2023 KHAING AYE
Grading Pre-Inspection Cleared 2/17/2023 KIRK LINKLATER
Coastal Zone Cleared 4/21/2023 MAYELA VILLA
ZI Cleared 4/21/2023 MAYELA VILLA

Contact Information

Contractor Owner-Builder       ,
Engineer Mcgahey,, Barbara; Lic. No.: C69216 28111 VIA DEL CERRO      SAN JUAN CAPISTRANO, CA 92675

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/24/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 11/15/2023 Corrections Issued ANSON MAGLASANG
Final 11/15/2023 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 11/15/2023 Corrections Issued ANSON MAGLASANG
Green Building Final 11/15/2023 Approved ANSON MAGLASANG
Smoke Detectors 11/15/2023 Approved ANSON MAGLASANG
Pre-Inspection 11/17/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 11/27/2023 Approved JAMES CHAVEZ
Final 11/27/2023 OK to Issue CofO JAMES CHAVEZ
Footing/Foundation/Slab 11/27/2023 Approved JAMES CHAVEZ