1014 N MARONEY LANE 90272
Certificate Information: 1014 N MARONEY LANE 90272
- Application / Permit
- 23014-30001-04077
- Plan Check / Job No.
- B25WL02502
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, Supplemental permit to 23014-30000-04077 FOR SINGLE-FAMILY DWELLING, NFPA 13(D) SPRINKLERS THROUGHOUT EO1 EXISTING FDN TO REMAIN
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | KAVIAN REFAHI |
| Corrections Issued | 3/30/2025 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/4/2025 | APPLICANT |
| Plan Check Approved | 5/19/2025 | KAVIAN REFAHI |
| Issued | 7/3/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/15/2025 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 4/15/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 4/15/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2025 | RYAN CASTRO |
Contact Information
| Architect | Waingrow,, Diane Alexandra; Lic. No.: C22308 | 1014 MARONEY LANE PACIFIC PALISADES, CA 90272 |
| Contractor | Palisades Construction Inc; Lic. No.: 531896-B | 2321 W OLIVE AVENUE, SUITE D BURBANK, CA 91506 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Mccullum,, Eric William; Lic. No.: C68850 | 727 2ND ST STE 104 HERMOSA BEACH, CA 90254 |
| Engineer | Sahebi,, Mo; Lic. No.: C33508 | 1330 OLYMPIC BL SANTA MONICA, CA 90404 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
| Landscape Architect | Perttula,, Tavi Ian; Lic. No.: LA5562 | 2341 27TH ST SANTA MONICA, CA 90405 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/10/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 7/30/2025 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/19/2025 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 12/22/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 1/22/2026 | Approved | BOBBY KEY |
| HVAC-Rough | 1/22/2026 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 2/4/2026 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 2/5/2026 | Corrections Issued | BOBBY KEY |
| Wood Frame | 2/5/2026 | Partial Approval | BOBBY KEY |
| FLOOD-Proofing Certificate | 2/12/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 2/12/2026 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 2/12/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Not Ready for Inspection | DANIEL VERA |